Jump to content

Moorabool Wind Farm: Difference between revisions

Coordinates: 37°42′S 144°12′E / 37.7°S 144.2°E / -37.7; 144.2
From Wikipedia, the free encyclopedia
Content deleted Content added
Adding Photo back
No edit summary
 
(7 intermediate revisions by 7 users not shown)
Line 3: Line 3:
{{Use dmy dates|date=October 2019}}
{{Use dmy dates|date=October 2019}}
{{infobox power station
{{infobox power station
| coordinates =
| image = Moorabool Wind Farm logo.png
| status = Operational
| coordinates = {{Coord|00|00|00|N|00|00|00|E|type:landmark|display=inline,title}}
| commissioned = 2022
}}
}}
'''Moorabool Wind Farm''' is a [[wind farm]] under construction between [[Ballarat]] and [[Geelong]] in [[Victoria (Australia)|Victoria]], Australia. It is expected to commence operation early in 2020. The wind farm is in two parts. The northern part has 50 turbines under construction and the southern part has 54. It is being developed by [[Goldwind Australia]].<ref>{{cite web |url=https://mooraboolwindfarm.com/ |title=Moorabool Wind Farm |publisher=[[Goldwind Australia]] |accessdate=5 October 2019}}</ref> When complete, Moorabool will be one of three wind farms in [[Moorabool Shire]]. The others are [[Yaloak South Wind Farm]] and [[Lal Lal Wind Farm]].<ref>{{cite web |url=https://www.moorabool.vic.gov.au/residents/community/windfarms-in-moorabool |title=Windfarms in Moorabool |publisher=[[Shire of Moorabool]] |accessdate=5 October 2019}}</ref>
'''Moorabool Wind Farm''' is an operational [[wind farm]] located 25 km southeast of [[Ballarat]] in [[Victoria (Australia)|Victoria]], Australia. The wind farm is in two parts: the northern part has 50 turbines, and the southern part has 54 turbines.<ref>{{Cite web|title=All turbines up at Goldwind's 312-MW Moorabool wind park |url=https://renewablesnow.com/news/all-turbines-up-at-goldwinds-312-mw-moorabool-wind-park-723350/|access-date=2021-11-16| website=Renewablesnow.com|language=en}}</ref> By December 2021, all 104 turbines had been put into place. The turbines each measure 169 m to the tip of the blade.


== Development and purpose ==
By 30 August 2019, all 54 foundations were completed in the southern section,<ref>{{cite web |url=https://mooraboolwindfarm.com/wp-content/uploads/2019/09/Moorabool-South-Progress-Map-August-30th-2019.pdf |title=South Wind Farm Construction Progress |date=30 August 2019 |publisher=[[Goldwind Australia]] |accessdate=5 October 2019}}</ref> and all the bases and 11 turbines were erected but not yet commissioned in the northern section.<ref>{{cite web |url=https://mooraboolwindfarm.com/wp-content/uploads/2019/09/Moorabool-North-Progress-Map-18th-September-2019.pdf |title=Moorabool North Wind Farm Construction Progress |date=18 September 2019 |publisher=[[Goldwind Australia]] |accessdate=5 October 2019}}</ref> The components for the southern section were to be delivered from the [[Port of Geelong]] in a total of 594 oversized loads at a rate of approximately 33 per week from September 2019 to February 2020.<ref>{{cite web |url=https://mooraboolwindfarm.com/wp-content/uploads/2019/08/MSWF-Oversize-Deliveries-Electronic.pdf |title=Turbine Component deliveries |publisher=[[Goldwind Australia]] |accessdate=5 October 2019}}</ref>
The farm is being developed by [[Goldwind Australia]].<ref name=":0">{{cite web |url=https://mooraboolwindfarm.com/ |title=Moorabool Wind Farm |publisher=[[Goldwind Australia]] |accessdate=5 October 2019}}</ref> When operational, it will be one of three wind farms in [[Moorabool Shire]]. The others are [[Yaloak South Wind Farm]] and [[Lal Lal Wind Farm]].<ref>{{cite web |url=https://www.moorabool.vic.gov.au/residents/community/windfarms-in-moorabool |title=Windfarms in Moorabool |publisher=[[Shire of Moorabool]] |accessdate=5 October 2019}}</ref>

When fully operational, the farm will produce up to 312MW of electricity, enough energy to power approximately 228,000 Victorian homes.<ref>{{Cite web|date=2020-12-07|title=Moorabool Wind Farm turbine installations complete|url=https://www.energymagazine.com.au/moorabool-wind-farm-turbine-installations-complete/|access-date=2021-11-16|website=Energy Magazine|language=en-US}}</ref>

The components for the southern section were delivered from the [[Port of Geelong]] in a total of 594 oversized loads at a rate of approximately 33 per week from September 2019 to February 2020.<ref>{{cite web |url=https://mooraboolwindfarm.com/wp-content/uploads/2019/08/MSWF-Oversize-Deliveries-Electronic.pdf |title=Turbine Component deliveries |publisher=[[Goldwind Australia]] |accessdate=5 October 2019}}</ref>

The wind farm commenced partial operation in late 2020. Commissioning was completed in 2022.<ref name=":0" />


==References==
==References==
Line 16: Line 24:
{{Energy in Victoria}}
{{Energy in Victoria}}


[[Category:Wind farms in Victoria (Australia)]]
[[Category:Wind farms in Victoria (state)]]

Latest revision as of 10:40, 22 April 2024

Moorabool Wind Farm
Map
Country
  • Australia
Location
Coordinates37°42′S 144°12′E / 37.7°S 144.2°E / -37.7; 144.2
StatusOperational
Construction began
  • July 2018
Commission date2022
Owner
Wind farm
Type
Power generation
Nameplate capacity
  • 321 MW
External links
Websitemooraboolwindfarm.com

Moorabool Wind Farm is an operational wind farm located 25 km southeast of Ballarat in Victoria, Australia. The wind farm is in two parts: the northern part has 50 turbines, and the southern part has 54 turbines.[1] By December 2021, all 104 turbines had been put into place. The turbines each measure 169 m to the tip of the blade.

Development and purpose

[edit]

The farm is being developed by Goldwind Australia.[2] When operational, it will be one of three wind farms in Moorabool Shire. The others are Yaloak South Wind Farm and Lal Lal Wind Farm.[3]

When fully operational, the farm will produce up to 312MW of electricity, enough energy to power approximately 228,000 Victorian homes.[4]

The components for the southern section were delivered from the Port of Geelong in a total of 594 oversized loads at a rate of approximately 33 per week from September 2019 to February 2020.[5]

The wind farm commenced partial operation in late 2020. Commissioning was completed in 2022.[2]

References

[edit]
  1. ^ "All turbines up at Goldwind's 312-MW Moorabool wind park". Renewablesnow.com. Retrieved 16 November 2021.
  2. ^ a b "Moorabool Wind Farm". Goldwind Australia. Retrieved 5 October 2019.
  3. ^ "Windfarms in Moorabool". Shire of Moorabool. Retrieved 5 October 2019.
  4. ^ "Moorabool Wind Farm turbine installations complete". Energy Magazine. 7 December 2020. Retrieved 16 November 2021.
  5. ^ "Turbine Component deliveries" (PDF). Goldwind Australia. Retrieved 5 October 2019.