Line 49: Line 49:


During the construction period the project would have sustained over 2,200 construction and manufacturing jobs,<ref>{{cite web|url=http://www.learningobservatory.com/sbtl|title=Swansea Bay Tidal Lagoon : Research : Access Latest LMI : Learning and Skills Observatory for Wales|website=www.learningobservatory.com|access-date=2016-12-07}}</ref> but in operation would only require 28 workers.<ref name="gov-20180625" /> The 2016 Hendry Review (the source of these figures) also considered the economic impact of two additional tidal lagoons: "Cardiff could support five times more total direct [[Full-time equivalent|FTE]]s than [Swansea Bay] (11,482); Colwyn Bay could support six times more (13,918)".<ref name=":2">{{Cite web|date=December 2016|title=The Role of Tidal Lagoons|url=https://hendryreview.files.wordpress.com/2016/08/hendry-review-final-report-english-version.pdf|access-date=18 November 2021|website=Hendry Review}}</ref>
During the construction period the project would have sustained over 2,200 construction and manufacturing jobs,<ref>{{cite web|url=http://www.learningobservatory.com/sbtl|title=Swansea Bay Tidal Lagoon : Research : Access Latest LMI : Learning and Skills Observatory for Wales|website=www.learningobservatory.com|access-date=2016-12-07}}</ref> but in operation would only require 28 workers.<ref name="gov-20180625" /> The 2016 Hendry Review (the source of these figures) also considered the economic impact of two additional tidal lagoons: "Cardiff could support five times more total direct [[Full-time equivalent|FTE]]s than [Swansea Bay] (11,482); Colwyn Bay could support six times more (13,918)".<ref name=":2">{{Cite web|date=December 2016|title=The Role of Tidal Lagoons|url=https://hendryreview.files.wordpress.com/2016/08/hendry-review-final-report-english-version.pdf|access-date=18 November 2021|website=Hendry Review}}</ref>
<blockquote class="twitter-tweet" data-lang="en"><p dir="ltr" lang="en">...just as gas plants and wind farms only create a small number of long-term jobs. The issue here was can we start a new global industry from the UK? Swansea would just be the start. Selective quotes from my Review do not enable us to have a proper debate. (Charles Hendry, 26 June 2018)<ref>{{cite tweet|user=charles_hendry|number=1011611091837779970|date=26 June 2018|title=... Swansea would just be the start. Selective quotes from my Review do not enable us to have a proper debate|author=Charles Hendry}}</ref></blockquote>
<blockquote class="twitter-tweet" data-lang="en"><p dir="ltr" lang="en">...just as gas plants and wind farms only create a small number of long-term jobs. The issue here was can we start a new global industry from the UK? Swansea would just be the start. Selective quotes from my Review do not enable us to have a proper debate. (Charles Hendry, 26 June 2018)<ref>{{cite tweet|user=charles_hendry|number=1011611091837779970|date=26 June 2018|title=... Swansea would just be the start. Selective quotes from my Review do not enable us to have a proper debate|author=Charles Hendry}}</ref></p></blockquote>


It would be constructed to withstand 500-year-storms and to function as a coastline protection against storms and floods.<ref>Shaun Waters, George Aggidis: ''A World First: Swansea Bay Tidal lagoon in review.'' In: ''[[Renewable and Sustainable Energy Reviews]]'' 56, (2016), 916–921, {{doi|10.1016/j.rser.2015.12.011}}.</ref>
It would be constructed to withstand 500-year-storms and to function as a coastline protection against storms and floods.<ref>Shaun Waters, George Aggidis: ''A World First: Swansea Bay Tidal lagoon in review.'' In: ''[[Renewable and Sustainable Energy Reviews]]'' 56, (2016), 916–921, {{doi|10.1016/j.rser.2015.12.011}}.</ref>
Line 102: Line 102:
[[Category:Nationally Significant Infrastructure Projects (United Kingdom)]]
[[Category:Nationally Significant Infrastructure Projects (United Kingdom)]]
[[Category:Cancelled projects in Wales]]
[[Category:Cancelled projects in Wales]]
[[Category:Proposed renewable energy power stations in Wales]]

Latest revision as of 01:01, 31 August 2024

Tidal Lagoon Swansea Bay
Map
CountryWales
LocationSwansea Bay
Coordinates51°35′52″N 3°54′23″W / 51.5977°N 3.9064°W / 51.5977; -3.9064
StatusFirst proposal rejected by the UK Government
Construction costProposal estimate £1.3 billion, Blue Eden: multi-billion pound project
OperatorTidal Lagoon (Swansea Bay) plc
Tidal power station
TypeTidal lagoon
Power generation
Nameplate capacity320 MW
External links
Websitewww.tidallagoonpower.com

Tidal Lagoon Swansea Bay was a proposed tidal lagoon power plant that was to be constructed in Swansea Bay off the south coast of Wales, United Kingdom. Development consent was granted by the UK government in June 2015, and in June 2018 the Welsh Government approved the plan and offered to invest £200 million; however, later that month the UK government withdrew its support on value-for-money grounds. Other options to enable the proposal to go ahead were reportedly still being explored.[1]

If built, the project would have become the world's first tidal lagoon power plant;[2] other types of tidal power plants do exist.[3][4]

Initial project proposals

[edit]

The scheme is promoted by Tidal Lagoon (Swansea Bay) plc. According to the company, generation could operate 14 hours per day with a maximum output of 320 MW (nameplate capacity),[5] enough to power around 155,000 homes.[6] There are different ways to evaluate tidal energy output. The UK government considered intermittency due to the tides and that the Tidal Lagoon Swansea Bay would have had a load factor of 19% compared to around 50% for offshore wind power.[7] However, as the monthly variation is predictable, tidal lagoon energy could allow reduction in the amount of energy generated by gas-fired power plants.[8]

During the construction period the project would have sustained over 2,200 construction and manufacturing jobs,[9] but in operation would only require 28 workers.[7] The 2016 Hendry Review (the source of these figures) also considered the economic impact of two additional tidal lagoons: "Cardiff could support five times more total direct FTEs than [Swansea Bay] (11,482); Colwyn Bay could support six times more (13,918)".[10]

It would be constructed to withstand 500-year-storms and to function as a coastline protection against storms and floods.[12]

The project was named as part of the UK Government's 2014 National Infrastructure Plan[13] and was granted development consent by the Department for Energy and Climate Change in June 2015, although the department stated that decisions relating to affordability were a separate matter.[2][14] In early June 2018 the Welsh Government offered to invest £200 million to improve the project's difficult business case.[15]

On 25 June 2018 the Department for Business, Energy and Industrial Strategy (BEIS) rejected a contract for difference electricity purchasing agreement necessary to fund the £1.3 billion proposal. The main reason given was that there was little cost reduction potential for future lagoons, and a series of lagoons would cost the average electricity consumer an additional £700 by between 2031 and 2050 compared to a mix of offshore wind and nuclear power projects.[16][7] The value for money calculation included the cost of all six of the proposed lagoons in the 35-year cost comparison.[7] A House of Commons Briefing Paper has tried to provide some context for MPs following the conflicting statements and views regarding the facts around tidal lagoons, the Swansea Bay proposal, and its rejection by the UK Government.[17]

The calculations and assumptions made by BEIS[18] which lie behind the rejection of the plan have been challenged by the company behind the proposal in an independently audited riposte[19] which intimates that misleading statements were put to the Parliamentary Joint Select Committee.[20] BEIS responded that the figures used are out of date.[21] The first report by the National Infrastructure Commission published on 11 July 2018 appears to exclude the role of any form of tidal power in the UK's future green energy mix in favour of wind, solar and electric cars based on a report by Aurora Energy Research looking at the market up to 2050. This states "Offshore wind becomes economical in the 2030s without subsidies, tidal never becomes competitive without government support". The Aurora Energy Research report also states "Amongst renewables, solar PV, onshore wind and offshore wind are the main sources of new renewables to enter economically under a carbon target. Building tidal power requires a subsidy, but the impact on total system cost is minimal".[22] These contrasting perspectives all use different time periods for modelling costs and benefits but a common thread is that a shorter time-frame flatters alternatives to tidal power and a longer time-frame flatters tidal power compared to its alternatives.[citation needed]

Proposed design

[edit]
  • 9.5 km of seawalls, impounding 11.5 km2 of the seabed[23]
  • 16 bidirectional turbines[23]
  • Each turbine 7.2 m in diameter[23]
  • Variable speed regulation claimed to reduce the harm to fish[24]

Roman concrete was proposed as a suitable material for constructing the sea walls.[25]

Finances

[edit]

Soon after the proposal was rejected by the UK Government, it was reported that the company behind the plan, owned by Mark Shorrock, was £23 million in debt and had spent £37 million on the proposal. One of the investors in Tidal Lagoon Swansea Bay was Good Energy, a firm led at that time by Shorrock's wife Juliet Davenport.[26] In return, Good Energy took a comprehensive charge over the project's assets, giving it a uniquely privileged class of shares compared to the other ordinary investors. Further questions have arisen out of the web of Shorrock-owned companies involved in the project, such as Tidal Lagoon plc which reportedly gave a loan to Tidal Lagoon Swansea Bay plc at a 20 per cent interest rate.[27]

Blue Eden

[edit]

Potential for a new project

[edit]

In January 2017 a government-commissioned review, published by Charles Hendry, gave backing to the technology's viability and the concept of tidal generation, but not specifically to this company's commercial proposal.[28][10] The economics of the Swansea Bay proposal have been criticised.[29] The effects on fish and wildlife were reportedly being assessed.[30]

In February 2019, the Guardian reported that a Swansea tidal lagoon plan had been revived without the need for government funding.[31] It is reported that Swansea-based Tidal Power plc has several major companies interested in buying the low-carbon electricity generated by the tide flowing through turbines in a concrete wall along Swansea Bay. Property company Land Securities, Cardiff Airport and property developer Berkeley Group are among those to have expressed an interest in signing a power purchase agreement (PPA) with the lagoon company.[31]

Blue Eden plans

[edit]

In January 2023, plans of a new Swansea tidal lagoon project called "Blue Eden" emerged but this time the multi-billion pound project would be fully funded by the private sector. Phase SA1 of the project is said to include an electric battery manufacturing plant, battery storage facility, a tidal lagoon in Swansea Bay with a floating solar farm, data storage centre, a green hydrogen production facility, an oceanic and climate change research centre, and hundreds of waterfront homes. Claimed it would be a worldwide first, the project could start within 18 months but would take more than a decade to complete.[32]

See also

[edit]

References

[edit]
  1. ^ McIntyre, Fiona (3 July 2018). "UK water industry 'could fund' £1.3bn Swansea Bay scheme". New Civil Engineer. Retrieved 23 August 2018.
  2. ^ a b Elsevier Ltd, The Boulevard, Langford Lane, Kidlington, Oxford, OX5 1GB, United Kingdom. "Green light for world's first tidal lagoon". renewableenergyfocus.com. Retrieved 26 July 2015.{{cite web}}: CS1 maint: multiple names: authors list (link) CS1 maint: numeric names: authors list (link)
  3. ^ "Tidal Power". EDF France. 27 May 2016. Retrieved 6 July 2018.
  4. ^ "World's Largest Tidal Power Plant–Shihwa Lake in Korea - Energy Korea". Energy Korea. Archived from the original on 8 August 2014. Retrieved 7 July 2018.
  5. ^ "Proposal overview & vision". Tidallagoonswanseabay.com. Retrieved 26 July 2015.
  6. ^ "Key Statistics - Tidal Lagoon". Tidal Lagoon. Retrieved 7 December 2016.
  7. ^ a b c d "Oral Statement to Parliament: Greg Clarke: Proposed Swansea Bay tidal lagoon". Department for Business, Energy and Industrial Strategy. 25 June 2018. Retrieved 26 June 2018.
  8. ^ MDPI paper: Grazia Todeschini, July 2017
  9. ^ "Swansea Bay Tidal Lagoon : Research : Access Latest LMI : Learning and Skills Observatory for Wales". www.learningobservatory.com. Retrieved 7 December 2016.
  10. ^ a b "The Role of Tidal Lagoons" (PDF). Hendry Review. December 2016. Retrieved 18 November 2021.
  11. ^ Charles Hendry [@charles_hendry] (26 June 2018). "... Swansea would just be the start. Selective quotes from my Review do not enable us to have a proper debate" (Tweet) – via Twitter.
  12. ^ Shaun Waters, George Aggidis: A World First: Swansea Bay Tidal lagoon in review. In: Renewable and Sustainable Energy Reviews 56, (2016), 916–921, doi:10.1016/j.rser.2015.12.011.
  13. ^ "Swansea Bay tidal lagoon given UK government boost". BBC News. 2 December 2014. Retrieved 26 July 2015.
  14. ^ "Swansea Bay Tidal Lagoon project gets green light on planning". GOV.UK. Department of Energy & Climate Change and Office of the Secretary of State for Wales. 9 June 2015. Retrieved 18 November 2021.
  15. ^ Williamson, David (5 June 2018). "Carwyn Jones offers to invest £200m as part of 'final offer' to save the Swansea lagoon". Wales Online. Retrieved 2 July 2018.
  16. ^ Adam Vaughanand Steven Morris (25 June 2018). "Government rejects plan for £1.3bn tidal lagoon in Swansea". The Guardian. Retrieved 26 June 2018. The inescapable conclusion of an extensive analysis is, however novel and appealing the proposal that has been made is … the cost that would be incurred by consumers and taxpayers would be so much higher than alternative sources of low-carbon power that it would be irresponsible to enter into a contract with the provider
  17. ^ Hinson, Suzanna (26 June 2018). Tidal lagoons (PDF). House of Commons Library (Report). UK Parliament. 7940. Retrieved 12 July 2018.
  18. ^ BEIS Tidal Lagoon power financial statement, June 2018
  19. ^ Audit of BEIS statement on Tidal Lagoons 10/07/2018
  20. ^ The BEIS Committee and the Welsh Affairs Committee: Swansea Bay Tidal Lagoon inquiry
  21. ^ Construction News, The Tidal Power Corner Comes out fighting, 11/07/2018
  22. ^ "Aurora Energy Research May 2018 for NIC" (PDF). Archived from the original (PDF) on 12 July 2018. Retrieved 11 July 2018.
  23. ^ a b c "Environmental Statement: Non-Technical Summary (6.1)" (PDF). Tidallagoon.opendebate.co.uk. Retrieved 6 July 2017.
  24. ^ Tidal Lagoon Power. "Turbine Technology". Tidallagoonpower.com. Retrieved 3 February 2017.
  25. ^ McGrath, Matt (4 July 2017). "Scientists explain ancient Rome's long-lasting concrete". Bbc.co.uk. Retrieved 5 July 2017.
  26. ^ Gosden, Emily (6 March 2016). "Meet the man who wants to be Britain's first tycoon of tides". The Telegraph. ISSN 0307-1235. Retrieved 18 November 2021.
  27. ^ "Keeping the lights on". Private Eye. London: Pressdram Ltd. 13 July 2018.
  28. ^ "Tidal lagoon: £1.3bn Swansea Bay project backed by review". BBC News. 12 January 2017. Retrieved 12 January 2017.
  29. ^ Jonathan Ford (15 January 2017). "(Paywall) Tidal power swamped by dubious mathematics". Financial Times. Retrieved 15 January 2017.
  30. ^ Swansea tidal lagoon review head Charles Hendry 'hopeful' BBC
  31. ^ a b Vaughan, Adam (4 February 2019). "Swansea tidal lagoon plan revived – without government funding". The Guardian. ISSN 0261-3077. Retrieved 14 February 2019.
  32. ^ "Green light expected for multi-billion-pound tidal lagoon project". Nation.Cymru. 12 January 2023. Retrieved 18 January 2023.