Hallandsås Tunnel: Difference between revisions
(34 intermediate revisions by 25 users not shown) | |||
Line 1: | Line 1: | ||
{{Short description|Railway Tunnel}} |
|||
{{Infobox tunnel |
{{Infobox tunnel |
||
|name = Hallandsås Tunnel |
|name = Hallandsås Tunnel |
||
|image = Hallandsåstunneln OSM zoom 11 220px.png |
|image = Hallandsåstunneln OSM zoom 11 220px.png |
||
|caption = The red, dotted line shows the tunnel. The red-white dashed line shows new, connecting railway, and the black-white dashed line shows the |
|caption = The red, dotted line shows the tunnel. The red-white dashed line shows new, connecting railway, and the black-white dashed line shows the previous railway stretch. |
||
|line = [[West Coast Line (Sweden)|West Coast Line]] |
|line = [[West Coast Line (Sweden)|West Coast Line]] |
||
|location = [[Båstad Municipality]], [[Skåne County]] |
|location = [[Båstad Municipality]], [[Skåne County]] |
||
|coordinates = |
|coordinates = |
||
|system = |
|system = |
||
|status = |
|status = Open |
||
|start = [[Förslöv]] {{coord|56|21|43|N|12|48|20|E|display=inline}} |
|start = [[Förslöv]] {{coord|56|21|43|N|12|48|20|E|display=inline}} |
||
|end = [[Båstad]] {{coord|56|25|28|N|12|53|20|E|display=inline}} |
|end = [[Båstad]] {{coord|56|25|28|N|12|53|20|E|display=inline}} |
||
|stations = |
|stations = |
||
|startwork = 1992 (restart 2003) |
|startwork = 1992 (restart 2003) |
||
|opened = 8 December 2015 |
|||
|open = ''2015'' (scheduled) |
|||
|close = |
|close = |
||
|owner = |
|owner = |
||
Line 31: | Line 32: | ||
|grade = |
|grade = |
||
}} |
}} |
||
[[File:Hallandsås northern opening.jpg|thumb|The northern opening of the Hallandsås tunnels.]] |
[[File:Hallandsås northern opening.jpg|thumb|The northern opening of the Hallandsås tunnels.]] |
||
[[File:Hallandsastunneln01 2006-07-08.jpg|thumb|The southern construction site; one of the two tunnel entrances can be seen in the background.]] |
[[File:Hallandsastunneln01 2006-07-08.jpg|thumb|The southern construction site; one of the two tunnel entrances can be seen in the background.]] |
||
The '''Hallandsås Tunnel''' ({{ |
The '''Hallandsås Tunnel''' ({{langx|sv|Hallandsåstunneln}}), also known as the '''Hallandsås Ridge Tunnel''' or '''Scanlink''', is a [[railway tunnel]] in Sweden. It connects the northern and the southern sides of the [[Hallandsås]] geological formation (a [[Horst (geology)|horst]]). The length is {{convert|8.7|km|mi|abbr=on}} ({{convert|8,722|m|ft|0|}} in one bore, {{convert|8,710|m|ft|0|}} in the other). It's utilised by the [[West Coast Line (Sweden)|West Coast Line]], on the section between [[Ängelholm]] and [[Halmstad]] in southwestern Sweden. It has improved the connection between the cities of [[Gothenburg]], Sweden, and [[Copenhagen]], Denmark. In the longer term it will be a key component in the [[proposed high-speed rail|proposed]] [[Oslo]] to [[Hamburg]] high speed rail link via Gothenburg, [[Malmö]] and Copenhagen. |
||
The project |
The project was troubled by construction difficulties caused by [[groundwater]] ingress, and a scandal when dangerous sealant materials were used causing workers to become ill and killing local fish and cattle. These caused the project to be halted from late 1997 to 2005, and resulted in large cost over-runs. The project was finished in December 2015, over 23 years after start of construction. |
||
== Background == |
== Background == |
||
The tunnel is part of a |
The tunnel is part of a larger project to upgrade the whole West Coast Line to [[double track]]. In the context of this project, the single-track stretch over the Hallandsås ridge was both too [[Minimum railway curve radius|curvy]] and [[Grade (slope)|steep]] to allow for easy double-track conversion and still allow for [[High-speed rail in Sweden|high-speed passenger trains]] and heavy freight trains. Additionally, this stretch contained 13 [[level crossing]]s, the single-track Båstad station, and a [[passing loop]] at [[Grevie]] at which trains must meet (and accumulate significant delays if one or both trains are late). In order to avoid this [[traffic bottleneck|bottleneck]], some passenger train services between [[Gothenburg]] and [[Malmö]], as well as most freight trains, took a long detour along the Halmstad–Hässleholm railway (which is also too steep for efficient freight traffic) and on the congested Hässleholm–Malmö railway. |
||
The Hallandsås Tunnel gives a time saving of 10 to 15 minutes for passenger trains. The capacity across the ridge will increase from 4 to 24 trains per hour (both directions together; in reality there will be 8-10 trains per hour in 2016). The tunnel project was conceived by the [[European Round Table of Industrialists]] and the newly formed [[Swedish Rail Administration]] (''Banverket'', now part of the [[Swedish Transport Administration]] or ''Trafikverket'') in the 1980s. |
|||
==Construction== |
==Construction== |
||
=== 1990s: Problems, scandal, and stoppage === |
=== 1990s: Problems, scandal, and stoppage === |
||
Construction began in 1992, and the traffic opening was originally planned for 1995. However, construction was plagued by major difficulties concerning large amounts of water seeping in from surrounding rock, only a small fraction of which had been foreseen. Additionally, the original drill broke down after drilling only {{convert|18|m|ft|0|abbr=on}}. |
Construction began in 1992, and the traffic opening was originally planned for 1995. However, construction was plagued by major difficulties concerning large amounts of water seeping in from surrounding rock, only a small fraction of which had been foreseen. Additionally, the original drill, which was said to drill 100 meters per week, broke down after drilling only {{convert|18|m|ft|0|abbr=on}}. The rock was too soft, so the machine could not use it to pull itself forward. The contractor tried to drill traditionally, but had to spend a lot of effort on sealing the water leaks. The contractor went bankrupt and a new contractor, Skanska, was contracted. The new contractor had similar trouble but a better contract that gave compensation for troublesome rock conditions. |
||
A scandal broke out when it was learned that a poisonous sealing compound ''[[Rhoca-Gil]]'' was used during construction. This substance was linked to the death of nearby livestock. Rhoca-Gil contains [[acrylamide]], a toxic chemical that is [[mutagen]]ic and possibly [[carcinogen]]ic. The main contractor, [[Skanska]], took no special precautions for the sealant, nor did it tell its own workers or the local population of the risks. By October 1997, local cattle and fish started dying and workers were becoming ill. The local press started an investigation. After tests were done showing high levels of acrylamide contamination, the site was declared a high risk zone and the sale of agricultural products from the region was banned. Skanska, along with [[Rhone-Poulenc]] and [[Statens Järnvägar|Swedish Railways]] all had criminal charges brought against them; some senior executives resigned as a result. |
|||
⚫ | Construction was halted in late 1997. By this time, nearly {{convert|3|km|mi|1|abbr=on}} had been bored in each tunnel: {{convert|1200|m|ft|0|abbr=on}} at the north end, {{convert|1700|m|ft|0|abbr=on}} at the south end, and {{convert|40|m|ft|0|abbr=on}} at the central [[adit]]).<ref>{{cite web|title=Construction|url=http://www.trafikverket.se/Privat/Projekt/Skane/Hallandsas/Byggnation/|work=Hallandsas Project|publisher=Trafikverket|language=Swedish|accessdate=6 November 2011}}</ref> |
||
⚫ | Construction was halted in late 1997. By this time, nearly {{convert|3|km|mi|1|abbr=on}} had been bored in each tunnel: {{convert|1200|m|ft|0|abbr=on}} at the north end, {{convert|1700|m|ft|0|abbr=on}} at the south end, and {{convert|40|m|ft|0|abbr=on}} at the central [[adit]]).<ref>{{cite web|title=Construction|url=http://www.trafikverket.se/Privat/Projekt/Skane/Hallandsas/Byggnation/|work=Hallandsas Project|publisher=Trafikverket|language=Swedish|accessdate=6 November 2011|archive-date=11 January 2012|archive-url=https://web.archive.org/web/20120111183140/http://www.trafikverket.se/Privat/Projekt/Skane/Hallandsas/Byggnation/|url-status=dead}}</ref> |
||
=== 2000s: Construction resumes === |
=== 2000s: Construction resumes === |
||
In 2005 construction resumed after a positive decision by the [[Riksdag]] and the [[Government of Sweden|Swedish government]], hydrological and environmental remediation by Banverket and Skanska, and selection of contracting consortium Skanska-Vinci for the project. A new completion date of 2012 was initially estimated, later being revised to 2015. |
In 2005 construction resumed after a positive decision by the [[Riksdag]] and the [[Government of Sweden|Swedish government]], hydrological and [[environmental remediation]] by Banverket and Skanska, and selection of contracting consortium Skanska-Vinci for the project. A new completion date of 2012 was initially estimated, later being revised to 2015. |
||
As the consortium decided to drill only one tunnel at a time, only one [[tunnel boring machine]] (TBM) was used for the revived project. Nicknamed "Åsa", the TBM was in reality a comprehensive tunnelling machine; as it drilled through the strata, it simultaneously installed precast concrete tunnel lining segments behind it, and then injected a mortar-and-gravel slurry into the voids between the strata and the lining. The problem of drilling through saturated rock and soil was tackled by drilling a pilot tunnel ahead of the TBM, then freezing the surrounding rock to a temperature of −40 °C (−40 °F), thereby guaranteeing solid strata for the TBM's progress.<ref name=trafconen>{{cite web|title=Construction technology|url=http://www.trafikverket.se/Om-Trafikverket/Andra-sprak/English-Engelska/Railway-and-Road/Railway-Construction-Projects/Hallandsas-Project/Construction-technology/|work=The Hallandsås Project|publisher=Trafikverket| |
As the consortium decided to drill only one tunnel at a time, only one [[tunnel boring machine]] (TBM) was used for the revived project. Nicknamed "Åsa", the TBM was in reality a comprehensive tunnelling machine; as it drilled through the strata, it simultaneously installed precast concrete tunnel lining segments behind it, and then injected a mortar-and-gravel slurry into the voids between the strata and the lining. The problem of drilling through saturated rock and soil was tackled by drilling a pilot tunnel ahead of the TBM, then freezing the surrounding rock to a temperature of −40 °C (−40 °F), thereby guaranteeing solid strata for the TBM's progress.<ref name=trafconen>{{cite web|title=Construction technology|url=http://www.trafikverket.se/Om-Trafikverket/Andra-sprak/English-Engelska/Railway-and-Road/Railway-Construction-Projects/Hallandsas-Project/Construction-technology/|work=The Hallandsås Project|publisher=Trafikverket|access-date=9 January 2013|url-status=dead|archive-url=https://web.archive.org/web/20140726004426/http://www.trafikverket.se/Om-Trafikverket/Andra-sprak/English-Engelska/Railway-and-Road/Railway-Construction-Projects/Hallandsas-Project/Construction-technology/|archive-date=26 July 2014}}</ref> |
||
=== 2010s: Breakthrough === |
=== 2010s: Breakthrough === |
||
On 25 August 2010, around 13:10 [[Central European Time|CET]], breakthrough was achieved in the eastern tunnel. Drilling then switched to the western tunnel, which started in March 2011 from the workface at the south end and proceeded north. On 3 April 2012, this drive reached the central adit, whereupon {{convert|2,517|m|ft|0|abbr=on}}, or 46 percent, of the western tunnel had been bored.<ref name=vaestadit>{{cite web|title=Tunnel construction through Hallandsås achieves new phase target|url=http://www.trafikverket.se/PageFiles/30982/Press_release_breakthrough_Mid_Adit_Hallandsas_Project_2012.pdf|work=The Hallandsås Project|publisher=Trafikverket|accessdate=1 May 2012}}</ref><ref>{{cite web |
On 25 August 2010, around 13:10 [[Central European Time|CET]], breakthrough was achieved in the eastern tunnel. Drilling then switched to the western tunnel, which started in March 2011 from the workface at the south end and proceeded north. On 3 April 2012, this drive reached the central adit, whereupon {{convert|2,517|m|ft|0|abbr=on}}, or 46 percent, of the western tunnel had been bored.<ref name=vaestadit>{{cite web|title=Tunnel construction through Hallandsås achieves new phase target|url=http://www.trafikverket.se/PageFiles/30982/Press_release_breakthrough_Mid_Adit_Hallandsas_Project_2012.pdf|work=The Hallandsås Project|publisher=Trafikverket|accessdate=1 May 2012}}{{dead link|date=September 2017 |bot=InternetArchiveBot |fix-attempted=yes }}</ref><ref>{{cite web|title=Hallandsås Project updates, week 17|url=http://www.trafikverket.se/Privat/Projekt/Skane/Hallandsas/Nyhetsarkiv-Hallandsas/Nyheter/201204/Lagesrapport-Projekt-Hallandsas-vecka-17/|work=The Hallandsås Project|publisher=Trafikverket|language=Swedish|access-date=1 May 2012|url-status=dead|archive-url=https://archive.today/20130418110059/http://www.trafikverket.se/Privat/Projekt/Skane/Hallandsas/Nyhetsarkiv-Hallandsas/Nyheter/201204/Lagesrapport-Projekt-Hallandsas-vecka-17/|archive-date=18 April 2013}}</ref> The remaining {{convert|1,144|m|ft|0|abbr=on}} to be drilled, which totaled 15 percent of the entire drilling project, was expected to be particularly challenging, as it contains a section of poor quality bedrock and significant amounts of water and water pressure.<ref name=vaestadit /> An extra freezing stage, plus extra time (4 to 6 months) allotted for freezing, and thicker concrete lining segments, was utilized in this {{convert|300|m|ft|0|abbr=on}} problem area, which is longer than the adjacent area encountered in the eastern bore.<ref>{{cite web|title=Freezing of the Mölleback zone|url=http://www.trafikverket.se/Privat/Projekt/Skane/Hallandsas/Byggnation/Byggteknik/Mollebackzonen/|work=The Hallandsas Project|publisher=Trafikverket|language=Swedish|access-date=4 June 2012|url-status=dead|archive-url=https://web.archive.org/web/20121111233525/http://www.trafikverket.se/Privat/Projekt/Skane/Hallandsas/Byggnation/Byggteknik/Mollebackzonen/|archive-date=11 November 2012}}</ref> On 4 September 2013, the second tunnel broke through.<ref>{{cite web|title=Hallandsås Project updates, week 35 |url=http://www.trafikverket.se/Privat/Projekt/Skane/Hallandsas/Nyhetsarkiv-Hallandsas/Nyheter/201308/Lagesrapport-Projekt-Hallandsas-vecka-35/language=Swedish| publisher=Trafikverkert| date= | accessdate=1 September 2013}} {{dead link|date=March 2014}}</ref><ref>[http://www.aftonbladet.se/nyheter/article17406217.ab Färdigborrat i dag på Hallandsåsen], from aftonbladet.se, accessed 4 September 2013</ref> |
||
There are 19 emergency cross-passages (including the central adit) between the two tunnels every {{convert|500|m|ft|0|abbr=on}}. These were bored and lined separately, a process completed in February 2014.<ref>{{cite web|title=Construction technology: Cross tunnels |
There are 19 emergency cross-passages (including the central adit) between the two tunnels every {{convert|500|m|ft|0|abbr=on}}. These were bored and lined separately, a process completed in February 2014.<ref>{{cite web|title=Construction technology: Cross tunnels|url=http://www.trafikverket.se/Privat/Projekt/Skane/Hallandsas/Byggnation/Byggteknik/Tvartunnlar/|work=The Hallandsås Project|publisher=Trafikverket|language=Swedish|access-date=9 January 2013|url-status=dead|archive-url=https://web.archive.org/web/20130112005054/http://www.trafikverket.se/Privat/Projekt/Skane/Hallandsas/Byggnation/Byggteknik/Tvartunnlar/|archive-date=12 January 2013}}</ref><ref>{{cite web|title=Hallandsås Project updates, week 8 (cross-passages)|url=http://www.trafikverket.se/Privat/Projekt/Skane/Hallandsas/Nyhetsarkiv-Hallandsas/Nyheter/201402/Lagesrapport-vecka-711/|work=The Hallandsås Project|publisher=Trafikverket|access-date=3 March 2014|language=Swedish|url-status=dead|archive-url=https://web.archive.org/web/20140305064547/http://www.trafikverket.se/Privat/Projekt/Skane/Hallandsas/Nyhetsarkiv-Hallandsas/Nyheter/201402/Lagesrapport-vecka-711/|archive-date=5 March 2014}}</ref> |
||
The opening ceremony was held on 8 December 2015, and the tunnel opened for traffic on 13 December.<ref>{{Cite web|title = Sweden finally opens its longest rail tunnel|url = http://www.railjournal.com/index.php/europe/sweden-finally-opens-its-longest-rail-tunnel.html?channel=537|website = www.railjournal.com| date=9 December 2015 |accessdate = 2015-12-09}}</ref> |
|||
There is a decision have an opening ceremony on 13 December 2015, and have six weeks closure on all traffic before that date in order to build the connection. |
|||
==Cost== |
==Cost== |
||
[[Cost overrun]] has been large. The cost was expected in 1992 to be 1 billion [[Swedish krona]] (SEK). The cost from 1992 to 1997 was in reality more than SEK 2 billion, for less than half the tunnel length. Since the remaining cost at the beginning of 2005 was calculated to be more than SEK 4 billion, there was initially much debate and hesitation as to whether to halt or resume work. The total cost is likely to reach over SEK 10.5 billion (approximately |
[[Cost overrun]] has been large. The cost was expected in 1992 to be 1 billion [[Swedish krona]] (SEK). The cost from 1992 to 1997 was in reality more than SEK 2 billion, for less than half the tunnel length. Since the remaining cost at the beginning of 2005 was calculated to be more than SEK 4 billion, there was initially much debate and hesitation as to whether to halt or resume work. The total cost is likely to reach over SEK 10.5 billion (approximately 1.25 billion USD as calculated in 2015), before the project is finished.<ref name=hallfaq>{{cite web|title=FAQ about the Hallandsås Project|url=http://www.trafikverket.se/PageFiles/30982/FAQ_eng.pdf|work=The Hallandsås Project|publisher=Trafikverket|access-date=20 January 2013|url-status=dead|archive-url=https://web.archive.org/web/20140309095418/http://www.trafikverket.se/PageFiles/30982/FAQ_eng.pdf|archive-date=9 March 2014}}</ref> |
||
== New stations == |
== New stations == |
||
As [[Båstad Municipality|Båstad]] station |
As [[Båstad Municipality|Båstad]] station was located on the old main line, a new station to the north of the tunnel's northern portal, located at {{coord|56|25|55|N|12|54|24|E}} and called '''Båstad N''' (Båstad North), replaced the old station. The bare platforms for Båstad N were built in the 1990s when the tunnel was first started, and finished during 2015. |
||
⚫ | |||
== Removal of the old railway == |
|||
⚫ | |||
On Nov 4, 2015 work was started to dismantle the old railway for re-use, recycling and disposal, and to rebuild the road surfaces at its crossings.<ref>{{cite web|title=Rivning av gamla järnvägen|url=http://bastad.se/kommun-samhalle/Hallandsastunneln/rivning-av-gamla-jarnvagen/|publisher=Båstad Municipality|language=Swedish|accessdate=2 January 2016}}{{dead link|date=September 2017 |bot=InternetArchiveBot |fix-attempted=yes }}</ref> |
|||
⚫ | |||
⚫ | |||
==References== |
==References== |
||
{{ |
{{Reflist}} |
||
==External links== |
==External links== |
||
* [http://www.trafikverket.se/Om-Trafikverket/Andra-sprak/English-Engelska/Railway-and-Road/Railway-Construction-Projects/Hallandsas-Project/ Trafikverket: The Hallandsås Project] |
* [https://web.archive.org/web/20130711023645/http://www.trafikverket.se/Om-Trafikverket/Andra-sprak/English-Engelska/Railway-and-Road/Railway-Construction-Projects/Hallandsas-Project/ Trafikverket: The Hallandsås Project] |
||
* [http://www.trafikverket.se/PageFiles/30982/Hallandsas_Project_in_brief.pdf Summary and timeline of the project] |
* [http://www.trafikverket.se/PageFiles/30982/Hallandsas_Project_in_brief.pdf Summary and timeline of the project]{{dead link|date=September 2017 |bot=InternetArchiveBot |fix-attempted=yes }} |
||
* [http://www.tunneltalk.com/Hallandsas-Aug10-Holethrough-number-1.php Hallandsås milestone achievement June 10, 2010] |
* [http://www.tunneltalk.com/Hallandsas-Aug10-Holethrough-number-1.php Hallandsås milestone achievement June 10, 2010] |
||
{{DEFAULTSORT:Hallandsas Tunnel}} |
{{DEFAULTSORT:Hallandsas Tunnel}} |
||
[[Category:Railway tunnels in Sweden]] |
[[Category:Railway tunnels in Sweden]] |
||
[[Category: |
[[Category:Rail infrastructure in Skåne County]] |
||
[[Category: |
[[Category:2015 establishments in Sweden]] |
||
[[Category:West Coast Line (Sweden)]] |
Latest revision as of 09:14, 30 October 2024
Overview | |
---|---|
Line | West Coast Line |
Location | Båstad Municipality, Skåne County |
Status | Open |
Start | Förslöv 56°21′43″N 12°48′20″E / 56.36194°N 12.80556°E |
End | Båstad 56°25′28″N 12°53′20″E / 56.42444°N 12.88889°E |
Operation | |
Work begun | 1992 (restart 2003) |
Opened | 8 December 2015 |
Traffic | Railway |
Technical | |
Length | 8.7 km (5.4 mi) |
The Hallandsås Tunnel (Swedish: Hallandsåstunneln), also known as the Hallandsås Ridge Tunnel or Scanlink, is a railway tunnel in Sweden. It connects the northern and the southern sides of the Hallandsås geological formation (a horst). The length is 8.7 km (5.4 mi) (8,722 metres (28,615 ft) in one bore, 8,710 metres (28,576 ft) in the other). It's utilised by the West Coast Line, on the section between Ängelholm and Halmstad in southwestern Sweden. It has improved the connection between the cities of Gothenburg, Sweden, and Copenhagen, Denmark. In the longer term it will be a key component in the proposed Oslo to Hamburg high speed rail link via Gothenburg, Malmö and Copenhagen.
The project was troubled by construction difficulties caused by groundwater ingress, and a scandal when dangerous sealant materials were used causing workers to become ill and killing local fish and cattle. These caused the project to be halted from late 1997 to 2005, and resulted in large cost over-runs. The project was finished in December 2015, over 23 years after start of construction.
Background
[edit]The tunnel is part of a larger project to upgrade the whole West Coast Line to double track. In the context of this project, the single-track stretch over the Hallandsås ridge was both too curvy and steep to allow for easy double-track conversion and still allow for high-speed passenger trains and heavy freight trains. Additionally, this stretch contained 13 level crossings, the single-track Båstad station, and a passing loop at Grevie at which trains must meet (and accumulate significant delays if one or both trains are late). In order to avoid this bottleneck, some passenger train services between Gothenburg and Malmö, as well as most freight trains, took a long detour along the Halmstad–Hässleholm railway (which is also too steep for efficient freight traffic) and on the congested Hässleholm–Malmö railway.
The Hallandsås Tunnel gives a time saving of 10 to 15 minutes for passenger trains. The capacity across the ridge will increase from 4 to 24 trains per hour (both directions together; in reality there will be 8-10 trains per hour in 2016). The tunnel project was conceived by the European Round Table of Industrialists and the newly formed Swedish Rail Administration (Banverket, now part of the Swedish Transport Administration or Trafikverket) in the 1980s.
Construction
[edit]1990s: Problems, scandal, and stoppage
[edit]Construction began in 1992, and the traffic opening was originally planned for 1995. However, construction was plagued by major difficulties concerning large amounts of water seeping in from surrounding rock, only a small fraction of which had been foreseen. Additionally, the original drill, which was said to drill 100 meters per week, broke down after drilling only 18 m (59 ft). The rock was too soft, so the machine could not use it to pull itself forward. The contractor tried to drill traditionally, but had to spend a lot of effort on sealing the water leaks. The contractor went bankrupt and a new contractor, Skanska, was contracted. The new contractor had similar trouble but a better contract that gave compensation for troublesome rock conditions.
A scandal broke out when it was learned that a poisonous sealing compound Rhoca-Gil was used during construction. This substance was linked to the death of nearby livestock. Rhoca-Gil contains acrylamide, a toxic chemical that is mutagenic and possibly carcinogenic. The main contractor, Skanska, took no special precautions for the sealant, nor did it tell its own workers or the local population of the risks. By October 1997, local cattle and fish started dying and workers were becoming ill. The local press started an investigation. After tests were done showing high levels of acrylamide contamination, the site was declared a high risk zone and the sale of agricultural products from the region was banned. Skanska, along with Rhone-Poulenc and Swedish Railways all had criminal charges brought against them; some senior executives resigned as a result.
Construction was halted in late 1997. By this time, nearly 3 km (1.9 mi) had been bored in each tunnel: 1,200 m (3,937 ft) at the north end, 1,700 m (5,577 ft) at the south end, and 40 m (131 ft) at the central adit).[1]
2000s: Construction resumes
[edit]In 2005 construction resumed after a positive decision by the Riksdag and the Swedish government, hydrological and environmental remediation by Banverket and Skanska, and selection of contracting consortium Skanska-Vinci for the project. A new completion date of 2012 was initially estimated, later being revised to 2015.
As the consortium decided to drill only one tunnel at a time, only one tunnel boring machine (TBM) was used for the revived project. Nicknamed "Åsa", the TBM was in reality a comprehensive tunnelling machine; as it drilled through the strata, it simultaneously installed precast concrete tunnel lining segments behind it, and then injected a mortar-and-gravel slurry into the voids between the strata and the lining. The problem of drilling through saturated rock and soil was tackled by drilling a pilot tunnel ahead of the TBM, then freezing the surrounding rock to a temperature of −40 °C (−40 °F), thereby guaranteeing solid strata for the TBM's progress.[2]
2010s: Breakthrough
[edit]On 25 August 2010, around 13:10 CET, breakthrough was achieved in the eastern tunnel. Drilling then switched to the western tunnel, which started in March 2011 from the workface at the south end and proceeded north. On 3 April 2012, this drive reached the central adit, whereupon 2,517 m (8,258 ft), or 46 percent, of the western tunnel had been bored.[3][4] The remaining 1,144 m (3,753 ft) to be drilled, which totaled 15 percent of the entire drilling project, was expected to be particularly challenging, as it contains a section of poor quality bedrock and significant amounts of water and water pressure.[3] An extra freezing stage, plus extra time (4 to 6 months) allotted for freezing, and thicker concrete lining segments, was utilized in this 300 m (984 ft) problem area, which is longer than the adjacent area encountered in the eastern bore.[5] On 4 September 2013, the second tunnel broke through.[6][7]
There are 19 emergency cross-passages (including the central adit) between the two tunnels every 500 m (1,640 ft). These were bored and lined separately, a process completed in February 2014.[8][9]
The opening ceremony was held on 8 December 2015, and the tunnel opened for traffic on 13 December.[10]
Cost
[edit]Cost overrun has been large. The cost was expected in 1992 to be 1 billion Swedish krona (SEK). The cost from 1992 to 1997 was in reality more than SEK 2 billion, for less than half the tunnel length. Since the remaining cost at the beginning of 2005 was calculated to be more than SEK 4 billion, there was initially much debate and hesitation as to whether to halt or resume work. The total cost is likely to reach over SEK 10.5 billion (approximately 1.25 billion USD as calculated in 2015), before the project is finished.[11]
New stations
[edit]As Båstad station was located on the old main line, a new station to the north of the tunnel's northern portal, located at 56°25′55″N 12°54′24″E / 56.43194°N 12.90667°E and called Båstad N (Båstad North), replaced the old station. The bare platforms for Båstad N were built in the 1990s when the tunnel was first started, and finished during 2015.
At the south end of the tunnel, two new stations for local trains (pågatåg) opened, Förslöv and Barkåkra station.
Removal of the old railway
[edit]There were plans for a station for local trains at Grevie on the old railway, but the Båstad Municipality would have been required to finance maintenance of that railway in that case, so these plans were dropped.
On Nov 4, 2015 work was started to dismantle the old railway for re-use, recycling and disposal, and to rebuild the road surfaces at its crossings.[12]
References
[edit]- ^ "Construction". Hallandsas Project (in Swedish). Trafikverket. Archived from the original on 11 January 2012. Retrieved 6 November 2011.
- ^ "Construction technology". The Hallandsås Project. Trafikverket. Archived from the original on 26 July 2014. Retrieved 9 January 2013.
- ^ a b "Tunnel construction through Hallandsås achieves new phase target" (PDF). The Hallandsås Project. Trafikverket. Retrieved 1 May 2012.[permanent dead link ]
- ^ "Hallandsås Project updates, week 17". The Hallandsås Project (in Swedish). Trafikverket. Archived from the original on 18 April 2013. Retrieved 1 May 2012.
- ^ "Freezing of the Mölleback zone". The Hallandsas Project (in Swedish). Trafikverket. Archived from the original on 11 November 2012. Retrieved 4 June 2012.
- ^ "Hallandsås Project updates, week 35". Trafikverkert. Retrieved 1 September 2013. [dead link ]
- ^ Färdigborrat i dag på Hallandsåsen, from aftonbladet.se, accessed 4 September 2013
- ^ "Construction technology: Cross tunnels". The Hallandsås Project (in Swedish). Trafikverket. Archived from the original on 12 January 2013. Retrieved 9 January 2013.
- ^ "Hallandsås Project updates, week 8 (cross-passages)". The Hallandsås Project (in Swedish). Trafikverket. Archived from the original on 5 March 2014. Retrieved 3 March 2014.
- ^ "Sweden finally opens its longest rail tunnel". www.railjournal.com. 9 December 2015. Retrieved 2015-12-09.
- ^ "FAQ about the Hallandsås Project" (PDF). The Hallandsås Project. Trafikverket. Archived from the original (PDF) on 9 March 2014. Retrieved 20 January 2013.
- ^ "Rivning av gamla järnvägen" (in Swedish). Båstad Municipality. Retrieved 2 January 2016.[permanent dead link ]