Ultra-Fast Broadband (New Zealand): Difference between revisions
Ballofstring (talk | contribs) Flagged that the article is out of date |
mNo edit summary |
||
Line 4: | Line 4: | ||
{{Update|date=March 2022|reason=The article needs to reflect the current progress of the rollout of UFB}} |
{{Update|date=March 2022|reason=The article needs to reflect the current progress of the rollout of UFB}} |
||
The '''Ultra-Fast Broadband''' initiative is a New Zealand Government programme of building [[Fiber to the x|fibre-to-the-home]] networks covering 87% of the population by the end of 2022. It is a [[public–private partnership]] of the government with four companies with total government investment of NZ$1.5 billion.<ref name="about">{{cite web| url=https://www.crowninfrastructure.govt.nz/about/| title=About| publisher=Crown Infrastructure Partners}}</ref> |
The '''Ultra-Fast Broadband''' initiative is a [[New Zealand]] Government programme of building [[Fiber to the x|fibre-to-the-home]] networks covering 87% of the population by the end of 2022. It is a [[public–private partnership]] of the government with four companies with total government investment of NZ$1.5 billion.<ref name="about">{{cite web| url=https://www.crowninfrastructure.govt.nz/about/| title=About| publisher=Crown Infrastructure Partners}}</ref> |
||
==Targets== |
==Targets== |
||
Line 129: | Line 129: | ||
==History== |
==History== |
||
The UFB project started as part of the National Party's [[2008 New Zealand general election|2008 election promise]] of an [[Internet in New Zealand#Ultra-Fast Broadband Initiative|Ultra-Fast Broadband Initiative]].<ref>{{cite web| url=http://www.med.govt.nz/templates/Page____42183.aspx| title=Crown Fibre Holdings| date=9 September 2010| publisher=MED}}</ref><ref>{{cite press release| url= http://www.beehive.govt.nz/release/crown+fibre+holdings+board+appointments | title=Crown Fibre Holdings Board appointments| first=Steven| last=Joyce| publisher=New Zealand Government| date=29 October 2009}}</ref> |
The UFB project started as part of the [[New Zealand National Party|National Party]]'s [[2008 New Zealand general election|2008 election promise]] of an [[Internet in New Zealand#Ultra-Fast Broadband Initiative|Ultra-Fast Broadband Initiative]].<ref>{{cite web| url=http://www.med.govt.nz/templates/Page____42183.aspx| title=Crown Fibre Holdings| date=9 September 2010| publisher=MED}}</ref><ref>{{cite press release| url= http://www.beehive.govt.nz/release/crown+fibre+holdings+board+appointments | title=Crown Fibre Holdings Board appointments| first=Steven| last=Joyce| publisher=New Zealand Government| date=29 October 2009}}</ref> |
||
Initially, the Ultra-Fast Broadband network would not be subject to the regulations placed on other telecommunications companies by the [[Commerce Commission]] until 2020. After protests by telecommunications companies, consumer groups and opposition parties,<ref>{{cite news| url= http://www.nbr.co.nz/article/eleven-telcos-consumer-groups-unite-against-crown-fibre-bill-ck-90449 | title=Eleven telcos, consumer groups unite against Crown Fibre bill| date=11 April 2011| work=National Business Review}}</ref> the government allowed Crown Fibre Holdings to be regulated by the Commerce Commission.<ref>{{cite press release| url= http://www.beehive.govt.nz/release/regulatory-forbearance-be-replaced | title=Regulatory forbearance to be replaced| date=18 May 2011| first=Steven| last=Joyce| publisher=New Zealand Government}}</ref> However, the government agreed to pay compensation to the partner companies if they lose money as a result of Commerce Commission regulation.<ref>{{cite news| url= http://www.nzherald.co.nz/business/news/article.cfm?c_id=3&objectid=10726351 | title=Joyce scraps regulatory holiday from broadband bill| date=18 May 2011| first=Adam| last=Bennett| work= [[The New Zealand Herald]]}}</ref> |
Initially, the Ultra-Fast Broadband network would not be subject to the regulations placed on other telecommunications companies by the [[Commerce Commission]] until 2020. After protests by telecommunications companies, consumer groups and opposition parties,<ref>{{cite news| url= http://www.nbr.co.nz/article/eleven-telcos-consumer-groups-unite-against-crown-fibre-bill-ck-90449 | title=Eleven telcos, consumer groups unite against Crown Fibre bill| date=11 April 2011| work=National Business Review}}</ref> the government allowed Crown Fibre Holdings to be regulated by the Commerce Commission.<ref>{{cite press release| url= http://www.beehive.govt.nz/release/regulatory-forbearance-be-replaced | title=Regulatory forbearance to be replaced| date=18 May 2011| first=Steven| last=Joyce| publisher=New Zealand Government}}</ref> However, the government agreed to pay compensation to the partner companies if they lose money as a result of Commerce Commission regulation.<ref>{{cite news| url= http://www.nzherald.co.nz/business/news/article.cfm?c_id=3&objectid=10726351 | title=Joyce scraps regulatory holiday from broadband bill| date=18 May 2011| first=Adam| last=Bennett| work= [[The New Zealand Herald]]}}</ref> |
Revision as of 22:43, 27 October 2022
This article needs to be updated. The reason given is: The article needs to reflect the current progress of the rollout of UFB.(March 2022) |
The Ultra-Fast Broadband initiative is a New Zealand Government programme of building fibre-to-the-home networks covering 87% of the population by the end of 2022. It is a public–private partnership of the government with four companies with total government investment of NZ$1.5 billion.[1]
Targets
The Ultra-Fast Broadband project plans to provide speeds of at least 100Mbit/s downstream and 50Mbit/s upstream, though upgradable to 10 times that speed.
It aims to have optical fibre available to all schools and public hospitals, most private health facilities and most businesses by 2015. Urban and suburban residential areas have fibre deployed gradually, with new development areas being a high priority.
Initially, the plan was to have fibre within reach of 75% of the population by 2019 with an investment of $1.35 billion. In August 2017, the government announced the target was to be expanded to 87% of the population and to be completed by 2022.[2]
Partner companies
Crown Fibre Holdings Limited (CFH) is a Crown-owned company set up to manage the project. CFH has contracted four companies to deploy fibre network.[3]
The main partner is Chorus, which won 69% of the roll out area.[1] Chorus was part of incumbent telco Spark but was split off into a separate company in order to participate in this project. CFH will invest NZ$929 million directly in Chorus with 50% being non-voting shares and 50% interest free loans.[4]
There are also three Local Fibre Companies (LFC). These are 50% owned by Crown Fibre and 50% by the local electricity lines company or local government. They are:
- Ultra Fast Fibre (13.7%), a partnership with lines company WEL Networks covering the central North Island including Hamilton, Cambridge, Te Awamutu, Tauranga, Tokoroa, New Plymouth, Hawera and Whanganui.
- Northpower Fibre (1.6%), a partnership with lines company Northpower covering Whangarei.
- Enable Networks (15.3%), a partnership with the Christchurch City Council through its trading arm CCHL covering the Christchurch, Rangiora, and Rolleston areas.[5]
The government aims to collect all the investment back in 2036. Due to the loan being interest free, the government expect this to cost $600m in opportunity cost.[6]
Technology
The technology used is gigabit-capable passive optical network (GPON) for residential customers, and point to point for large businesses. Dark fibre is also available.
Chorus or the LFCs wholesale services to ISPs, who in turn offer services to their customers. There are 89 retail providers offering UFB services.[7]
The original contract between CFH and the fibre network companies specifies that there are to be wholesale residential plans of 30Mbit/s download with 10Mbit/s upload and 100Mbit/s download with 50Mbit/s upload.
The fibre network companies also offer other residential and business plans. A gigabit residential service of up to 1Gbit/s download and 500Mbit/s upload and Business gigabit services (with higher CIR (committed information rates) are available in all UFB areas.
As of June 2018[update], unlimited residential UFB plans start from NZ$69.00 for 30Mbps download / 10 Mbps upload (50/10 at same cost in Chorus areas[8]) NZ$72.00 for 100Mbps download / 20 Mbps upload (200/20 at same cost in Enable areas starting 1 July 2018[9] ) and NZ$99.99 for 1000Mbps download / 500 Mbps upload.[10]
Chorus reports that 76% of mass market fibre plans now sold are 100Mbps or faster and the average monthly data use by a fibre customer is 250GB.[11]
Customers must arrange the final connection to the UFB network with their ISP, who in turn arranges connection with the relevant fibre network company. The fibre network company then installs the fibre lead-in from the street to the customer's premises, the external termination point (ETP) and the optical network terminal (ONT). If the fibre lead-in needs to travel along shared rights of way or through cross-lease land, all affected neighbours must consent to the installation. The standard ONT provides four gigabit Ethernet ports and two ATA phone ports. It is also possible to have ONTs that provide WiFi, or radio over fiber.
For each area an ISP wishes to serve, it needs to put in a handover point and organize a backhaul link back to its core network. (There are 33 points of interconnect (POIs), one for each UFB candidate area.) Therefore, only a few ISPs offer nationwide UFB services, and the majority only focus in a few areas. This is different to DSL, where Chorus can deliver all of an ISP's customers nationwide to a single handover point, so ISPs can easily offer nationwide DSL service.[12]
Progress
The initial UFB project consisted of 33 areas covering 75% of the population and was completed at the end of 2019.
UFB2 (January 2017) will provide fibre to more than 151 new towns bringing coverage up to 85% of the population to be complete by the end of 2022.
UFB2+ (August 2017) will provide fibre to more than 190 new towns bringing coverage up to 87% of the population with the UFB2/2+ project to be fully rolled out by end of 2024.
The complete list of all UFB locations is available on the Crown Infrastructure Partners website.
As of November 2019[update], the original UFB project is 100% complete, with an uptake of 55% [1]
UFB 1 area | Provider | Premises able to connect[13] |
Premises connected[13] |
Completed/Planned[14] |
---|---|---|---|---|
Whangarei | Northpower | 23,012 | 50.3% | 8 May 2014[15] |
Auckland | Chorus | 442,081 | 47.5% | 2019 |
Waiheke Island | Chorus | 5,691 | 39.6% | 2017 |
Pukekohe | Chorus | 8,271 | 45.1% | 2018 |
Waiuku | Chorus | 3,645 | 54.1% | 19 May 2016[16] |
Hamilton | UFF | 67,016 | 52.3% | 7 April 2016[17] |
Cambridge | UFF | 8,670 | 49.9% | 13 February 2015[18] |
Te Awamutu | UFF | 5,917 | 46.5% | 3 October 2014[19] |
Tauranga | UFF | 60,975 | 53.2% | 11 March 2016[20] |
Rotorua | Chorus | 26,710 | 47.6% | 17 June 2016[21] |
Tokoroa | UFF | 5,473 | 42.3% | 13 February 2015[18] |
Taupo | Chorus | 13,503 | 39.7% | 15 May 2015[22] |
Whakatane | Chorus | 7,141 | 40.7% | 23 September 2016[23] |
Gisborne | Chorus | 14,797 | 28.8% | 2018 |
Napier-Hastings | Chorus | 41,960 | 38.9% | 2019 |
New Plymouth | UFF | 26,774 | 49.7% | 19 February 2016[24] |
Hawera | UFF | 4,943 | 46.7% | 13 February 2015[18] |
Whanganui | UFF | 20,851 | 37.6% | 18 April 2015[25] |
Palmerston North | Chorus | 32,240 | 42.2% | 2019 |
Feilding | Chorus | 6,617 | 38.3% | 2018 |
Levin | Chorus | 8,507 | 40.1% | 2017 |
Masterton | Chorus | 9,608 | 44.5% | 3 December 2015[26] |
Kapiti | Chorus | 14,893 | 22.8% | 2019 |
Wellington | Chorus | 147,144 | 34.4% | 2019 |
Nelson | Chorus | 26,413 | 52.3% | 2017 |
Blenheim | Chorus | 13,145 | 50.0% | 20 March 2015[27] |
Greymouth | Chorus | 4,337 | 43.3% | 26 November 2015[28] |
Christchurch metro [nb 1] | Enable | 197,700 | 39.0% | 30 May 2018[9] |
Ashburton | Chorus | 9,216 | 44.1% | 13 March 2015[29] |
Timaru | Chorus | 14,613 | 48.3% | 30 April 2015[30] |
Oamaru | Chorus | 6,747 | 41.7% | 15 December 2014[31] |
Dunedin | Chorus | 53,291 | 51.3% | 22 June 2018[32] |
Queenstown | Chorus | 7,989 | 45.2% | 29 July 2016 [33] |
Invercargill | Chorus | 24,916 | 41.5% | 2018 |
History
The UFB project started as part of the National Party's 2008 election promise of an Ultra-Fast Broadband Initiative.[34][35]
Initially, the Ultra-Fast Broadband network would not be subject to the regulations placed on other telecommunications companies by the Commerce Commission until 2020. After protests by telecommunications companies, consumer groups and opposition parties,[36] the government allowed Crown Fibre Holdings to be regulated by the Commerce Commission.[37] However, the government agreed to pay compensation to the partner companies if they lose money as a result of Commerce Commission regulation.[38]
In 2015, the Government released a discussion document which sought views on how prices for UFB services should be set after 2019.[39] The discussion paper ultimately resulted in the Telecommunications (New Regulatory Framework) Amendment Bill, which was passed in late 2018.[40]
References
- ^ a b "About". Crown Infrastructure Partners.
- ^ "Ultra Fast Broadband Extension (UFB2)". Crown Infrastructure. 30 August 2017.
- ^ "Crown Partners". Crown Fibre Holdings. Retrieved 24 January 2016.
- ^ Fletcher, Hamish (25 May 2011). "Green light for two Telecoms". The New Zealand Herald.
- ^ Harvie, Will (2 July 2016). "The underground anchor project". The Press. pp. C1–C2. Retrieved 3 July 2016.
- ^ Pullar-Strecker, Tom (24 May 2011). "$600 million UFB's 'true cost'". The Dominion Post. Stuff. Archived from the original on 7 August 2017. Retrieved 7 August 2017.
- ^ "Deployment progress". Ministry of Economic Development. 15 February 2016.
- ^ "Increasing entry level residential plans to 50Mbps – Chorus Service Provider". sp.chorus.co.nz.
- ^ a b "Enable doubles fibre broadband speeds celebrating completion of network across greater Christchurch – Enable". www.enable.net.nz.
- ^ "Compare Fibre Broadband Plans in New Zealand". www.glimp.co.nz.
- ^ "Reports – Corporate Website". company.chorus.co.nz.
- ^ Ritchie, Brendan (11 December 2012). "Why No Aggregated National Port Option From UFB/NBN?". DTS Limited. Retrieved 18 May 2015.
- ^ a b "Broadband Deployment Update – June 2018" (PDF). MBIE.
- ^ CFH Statement of Intent July 2014 – June 2018 (PDF). June 2014. p. 14. Retrieved 17 May 2015.
- ^ Dinsdale, Mike (9 May 2014). "Speeding ahead as first ultra-fast city". Northern Advocate. Retrieved 17 May 2015.
- ^ Barker, Sara (19 May 2016). "Waiuku 17th New Zealand town to get ultra fast broadband". IT Brief NZ. Retrieved 29 July 2015.
- ^ Adams, Amy (7 April 2016). "Faster broadband for Hamilton". Beehive.govt.nz. New Zealand Government. Retrieved 8 April 2016.
- ^ a b c "Ultrafast Fibre connects three more towns". Crown Fibre. 13 February 2015. Retrieved 17 May 2015.
- ^ "Te Awamutu high-speed broadband rollout completed". Ultrafast Fibre Ltd. 3 October 2014. Retrieved 17 May 2015.
- ^ Adams, Amy. "Tauranga fully-fibred and raring to go". beehive.govt.nz. NZ Government. Retrieved 11 March 2016.
- ^ Porter, David (17 June 2016). "Rotorua's broadband rollout complete". Rotorua Daily Post. Retrieved 29 July 2015.
- ^ "Taupo's ultra fast network complete". Rotorua Daily Post. 15 May 2015. Retrieved 17 May 2015.
- ^ "UFB build completed in Whakatane". Chorus. 23 September 2016. Retrieved 13 April 2018.
- ^ Adams, Amy (19 February 2016). "New Plymouth fully connected to Ultra-Fast Broadband". beehive.govt.nz. NZ Government. Retrieved 11 March 2016.
- ^ Wilson, Zaryd (20 April 2015). "Fibre to boost network speed". Wanganui Chronicle. Retrieved 17 May 2015.
- ^ Fuller, Piers (3 December 2015). "Amy Adams announces full UFB fibre rollout for Masterton". The Dominion Post. Retrieved 29 July 2015.
- ^ Hill, Helen (20 March 2015). "Blenheim homes all able to access UFB". The Marlborough Express. Stuff. Retrieved 17 May 2015.
- ^ Adams, Amy (26 November 2015). "Greymouth joins ranks of fully-fibred towns" (Press release). New Zealand Government. Retrieved 29 November 2015.
- ^ "Chorus completes UFB rollout in Ashburton". Crown Fibre. 13 March 2015. Retrieved 17 May 2015.
- ^ Malone, Audrey (30 April 2015). "Ultra fast broadband rollout in Timaru complete". The Timaru Herald. Stuff. Retrieved 17 May 2015.
- ^ Bruce, David (16 December 2015). "Urged to take up benefits of UFB". Otago Daily Times. Retrieved 17 May 2015.
- ^ "Chorus completes fibre build in Dunedin, South Island UFB1 complete". www.voxy.co.nz.
- ^ Adams, Amy (29 July 2016). "Queenstown UFB rollout now complete" (Press release). New Zealand Government. Retrieved 29 July 2016.
- ^ "Crown Fibre Holdings". MED. 9 September 2010.
- ^ Joyce, Steven (29 October 2009). "Crown Fibre Holdings Board appointments" (Press release). New Zealand Government.
- ^ "Eleven telcos, consumer groups unite against Crown Fibre bill". National Business Review. 11 April 2011.
- ^ Joyce, Steven (18 May 2011). "Regulatory forbearance to be replaced" (Press release). New Zealand Government.
- ^ Bennett, Adam (18 May 2011). "Joyce scraps regulatory holiday from broadband bill". The New Zealand Herald.
- ^ "Review of the Telecommunications Act 2001". Ministry of Business, Innovation and Employment. Retrieved 9 March 2016.
- ^ "Telecommunications (New Regulatory Framework) Amendment Bill – New Zealand Parliament". Retrieved 13 November 2018.
External links
- Crown Fibre Holdings
- Ultra-Fast Broadband Initiative, Ministry of Business, Innovation & Employment
Builders of the UFB network