Construction began in February 2020.<ref name="5R"/> Commercial commissioning took place in June 2021.<ref name="2R"/>
Construction began in February 2020.<ref name="5R"/> Commercial commissioning took place in June 2021.<ref name="2R"/>

==Expansion==
In November 2022, AMEA Power Company, the Dubai-based IPP, secured a US$25 million loan for the purpose of increasing capacity of the power station from 50 MW to 70 MW. In addition a battery storage facility, rated at 4 MWh will be added to the installation, to facilitate power supply after sunset. The EPC contractor for the expansion and energy storage installation is Amea Power's subsidiary, Amea Technical Services. The loan was provided by the [[Abu Dhabi Export Office]] (ADEX), a "financial facility of the [[Abu Dhabi Fund for Development]] (ADFD)".<ref name="ExpR">{{cite web|url=https://www.afrik21.africa/en/togo-blitta-solar-pv-plant-capacity-to-be-increased-to-70-mwp/ |
title=Togo: Blitta Solar PV Plant Capacity To Be Increased To 70 MWp |work=Afrik21.africa |date=24 November 2022 |author=Jean Marie Takouleu |access-date=30 November 2022 |location=Paris, France}}</ref>


==See also==
==See also==

Revision as of 16:14, 30 November 2022

Blitta Solar Power Station
Map
Official nameMohamed Bin Zayed Power Station
CountryTogo
LocationBlitta, Centrale Region
Coordinates08°18′28″N 01°00′37″E / 8.30778°N 1.01028°E / 8.30778; 1.01028
StatusOperational
Construction beganQ1 2020
Commission dateQ2 2021
Construction cost€33.5 million
OwnerAmea Power
OperatorAmea Togo Solar
Solar farm
TypeFlat-panel PV
Power generation
Nameplate capacity50 MW (67,000 hp)

The Blitta Solar Power Station is an operational 50 MW (67,000 hp) solar power plant in Togo. The power station was developed by Amea Power, an independent power producer (IPP), based in the United Arab Emirates. The solar farm, which is the largest grid-ready in Togo, is also referred to as Mohamed Bin Zayed Power Station, named after His Highness Sheikh Mohamed bin Zayed Al Nahyan, the Crown Prince of Abu Dhabi. The power station began commercial operations in June 2021.[1][2]

Location

The power station is located in the settlement of Blitta, in the Centrale Region of Togo, approximately 83.5 kilometres (51.9 mi), by road, south of Sokodé, the regional capital.[3] This is approximately 267 kilometres (166 mi) by road north of Lomé, the national capital and largest city in the country.[4]

Overview

The power station's installed capacity is 50 megawatts. Its output is sold directly to the government of Togo for integration into the national electricity grid, under a 25-year power purchase agreement. The solar park will be operated and maintained by Amea Togo Solar, the local subsidiary of Amea Power, the UAE-based IPP that owns the power station. It is expected that the power station will provide electricity to 600,000 homes and 700 small and medium-sized enterprises, in Togo.[5]

Developers

The power station was developed by Amea Power, an independent power producer based in the United Arab Emirates. The solar park is operated by Amea Togo Solar, the local subsidiary of the Middle Eastern owners.[5]

Funding and timeline

The table below outlines the sources of funding for the construction of this power station.[5]

Sources of Funds For Construction of Blitta Solar Power Station
Rank Development Partner Contribution in Euros Percentage Notes
1 Abu Dhabi Fund for Development 13.6 million 40.60 Loan
2 West African Development Bank 10.7 million 31.94 Loan
3 Amea Power 9.2 million 27.46 Equity Investment
Total 33.5 million 100.00

Construction began in February 2020.[5] Commercial commissioning took place in June 2021.[2]

Expansion

In November 2022, AMEA Power Company, the Dubai-based IPP, secured a US$25 million loan for the purpose of increasing capacity of the power station from 50 MW to 70 MW. In addition a battery storage facility, rated at 4 MWh will be added to the installation, to facilitate power supply after sunset. The EPC contractor for the expansion and energy storage installation is Amea Power's subsidiary, Amea Technical Services. The loan was provided by the Abu Dhabi Export Office (ADEX), a "financial facility of the Abu Dhabi Fund for Development (ADFD)".[6]

See also

References

  1. ^ Africa Global Funds (22 June 2021). "AMEA Power launches 50MW solar power plant in Togo". Africa Global Funds. Retrieved 25 June 2021.
  2. ^ a b Jean Marie Takouleu (24 June 2021). "Togo: In Blitta, the largest solar park in West Africa is now operational". Afrik21.africa. Paris, France. Retrieved 25 June 2021.
  3. ^ "Road Distance Between Sokodé, Togo And Blitta, Togo" (Map). Google Maps. Retrieved 25 June 2021.
  4. ^ "Road Distance Between Lomé, Togo And Blitta, Togo" (Map). Google Maps. Retrieved 25 June 2021.
  5. ^ a b c d Jean Marie Takouleu (6 February 2020). "Togo: Amea Power starts construction work for Blitta solar power plant". Afrik.21.africa. Paris, France. Retrieved 26 June 2021.
  6. ^ Jean Marie Takouleu (24 November 2022). "Togo: Blitta Solar PV Plant Capacity To Be Increased To 70 MWp". Afrik21.africa. Paris, France. Retrieved 30 November 2022.