Jump to content

Muskrat Falls Generating Station: Difference between revisions

Coordinates: 53°14′44″N 60°46′22″W / 53.24556°N 60.77278°W / 53.24556; -60.77278
From Wikipedia, the free encyclopedia
Content deleted Content added
Line 72: Line 72:
In 2017, [[Premier of Newfoundland and Labrador|Premier]] Dwight Ball called a public inquiry into the project,<ref>{{cite web|url=https://www.theglobeandmail.com/news/national/newfoundland-premier-announces-inquiry-into-muskrat-falls-project/article36431531/|title=Newfoundland Premier announces inquiry into Muskrat Falls project|publisher=The Globe and Mail|date=September 29, 2017|first=Andrew|last=Vaughan|access-date=Nov 29, 2020}}</ref> which took place between 2018 and 2020.<ref>{{Cite web|url=https://www.releases.gov.nl.ca/releases/2017/exec/1120n05.aspx|title=Premier Ball Announces Muskrat Falls Public Inquiry|publisher=Government of Newfoundland and Labrador|language=en|date=November 20, 2017|access-date=Nov 29, 2020}}</ref> In the inquiry report, Commissioner Richard LeBlanc concluded the government failed its duty to residents by predetermining that the megaproject would proceed no matter what. In his report, LeBlanc concluded that the business case, which assumed the Muskrat Falls project was the lowest-cost power option, was “questionable.” LeBlanc said that the project’s economics were not sufficiently tested and that Nalcor failed to consider all potentially viable power options. LeBlanc said that Nalcor concealed information that could have undermined the business case for the project from the public and government.<ref>{{cite web|url=https://www.theglobeandmail.com/canada/article-nl-government-to-release-final-report-from-muskrat-falls-inquiry/|title=Final report from Muskrat Falls inquiry released to the public|publisher=The Globe and Mail|date=March 10, 2020|first=Holly|last=McKenzie-Sutter|access-date=Nov 29, 2020}}</ref>
In 2017, [[Premier of Newfoundland and Labrador|Premier]] Dwight Ball called a public inquiry into the project,<ref>{{cite web|url=https://www.theglobeandmail.com/news/national/newfoundland-premier-announces-inquiry-into-muskrat-falls-project/article36431531/|title=Newfoundland Premier announces inquiry into Muskrat Falls project|publisher=The Globe and Mail|date=September 29, 2017|first=Andrew|last=Vaughan|access-date=Nov 29, 2020}}</ref> which took place between 2018 and 2020.<ref>{{Cite web|url=https://www.releases.gov.nl.ca/releases/2017/exec/1120n05.aspx|title=Premier Ball Announces Muskrat Falls Public Inquiry|publisher=Government of Newfoundland and Labrador|language=en|date=November 20, 2017|access-date=Nov 29, 2020}}</ref> In the inquiry report, Commissioner Richard LeBlanc concluded the government failed its duty to residents by predetermining that the megaproject would proceed no matter what. In his report, LeBlanc concluded that the business case, which assumed the Muskrat Falls project was the lowest-cost power option, was “questionable.” LeBlanc said that the project’s economics were not sufficiently tested and that Nalcor failed to consider all potentially viable power options. LeBlanc said that Nalcor concealed information that could have undermined the business case for the project from the public and government.<ref>{{cite web|url=https://www.theglobeandmail.com/canada/article-nl-government-to-release-final-report-from-muskrat-falls-inquiry/|title=Final report from Muskrat Falls inquiry released to the public|publisher=The Globe and Mail|date=March 10, 2020|first=Holly|last=McKenzie-Sutter|access-date=Nov 29, 2020}}</ref>


In July 2021, [[Prime Minister of Canada|Prime Minister]] [[Justin Trudeau]] announced that the [[Government of Canada]] would provide the project with $5.2 billion of financial support to compensate for its large cost overrun (from $6.2 billion to over $13 billion) and to enable the province to maintain the price of power at a competitive rate (14.7 cents per kilowatt-hour).<ref>{{Cite web|date=July 28, 2021|title=$5.2B deal reached between feds, N.L. government to stave off skyrocketing power bills|url=https://www.cbc.ca/news/canada/newfoundland-labrador/rate-mitigation-muskrat-falls-trudeau-furey-announcement-1.6120454|website=[[CBC News]]}}</ref><ref>{{Cite web|date=July 27, 2021|title=Ottawa to give N.L. billions of dollars to offset Muskrat Falls costs|url=https://www.cbc.ca/news/politics/muskrat-falls-hydro-newfoundland-labrador-1.6119276|website=[[CBC News]]}}</ref> The [[government of Quebec]] protested against this subsidy, which they claim provides unfair competition to their own [[Hydro Québec]] power company.<ref>{{cite web|url=https://thenarwhal.ca/muskrat-falls-hydro-dam-trudeau-bailout/ |title=Trudeau offers $5.2 billion bailout for Newfoundland and Labrador’s beleaguered Muskrat Falls hydro dam|publisher=The Narwhal (Victoria, BC)|date=July 29, 2021 |access-date=Oct 16, 2022|quote =Meanwhile, the Bloc Quebecois is decidedly against the bailout. It sees the money as an unfair advantage to N.L., because Hydro-Quebec and Nalcor are both Crown corporations with significant hydropower competing for New England markets...“In launching this project, the Newfoundland government made no secret of the fact that its objective was to harm Quebec, bypass Quebec territory and compete with Hydro-Quebec on export markets. “By announcing such funding, the government of Justin Trudeau is directly attacking Hydro-Quebec, which has been trying for several years to increase its electricity sales in the United States, one of the markets targeted by Muskrat Falls,” the statement also reads. Hydro-Quebec declined comment.}}</ref> The [[Sheshatshiu Innu First Nation|Innu Nation]] protested the decision stating they had not been consulted.<ref>{{Cite web|date=Oct 14, 2021|title=Innu Nation repeatedly blindsided by Muskrat Falls announcements, letters show|url=https://www.cbc.ca/news/canada/newfoundland-labrador/innu-nation-not-tolerate-consultations-1.6209097|website=[[CBC News]]}}</ref> The Innu Nation also raised concerns about the compensation claimed by the [[Innu]] and how cost overruns may reduce the amount of Innu royalties received under the 2011 impact and benefits agreement.<ref>{{Cite web|date=Aug. 03, 2021|title=Muskrat Falls deal 'betrayed the Innu people,' says Innu Nation|url=https://www.cbc.ca/news/canada/newfoundland-labrador/innu-nation-muskrat-falls-agreement-1.6127949|website=[[CBC News]]}}</ref>
In July 2021, [[Prime Minister of Canada|Prime Minister]] [[Justin Trudeau]] announced that the [[Government of Canada]] would provide the project with $5.2 billion of financial support to compensate for its large cost overrun (from $6.2 billion to over $13 billion) and to enable the province to maintain the price of power at a competitive rate (14.7 cents per kilowatt-hour).<ref>{{Cite web|date=July 28, 2021|title=$5.2B deal reached between feds, N.L. government to stave off skyrocketing power bills|url=https://www.cbc.ca/news/canada/newfoundland-labrador/rate-mitigation-muskrat-falls-trudeau-furey-announcement-1.6120454|website=[[CBC News]]}}</ref><ref>{{Cite web|date=July 27, 2021|title=Ottawa to give N.L. billions of dollars to offset Muskrat Falls costs|url=https://www.cbc.ca/news/politics/muskrat-falls-hydro-newfoundland-labrador-1.6119276|website=[[CBC News]]}}</ref> The [[government of Quebec]] and [[Bloc Québécois]] [[Members of Parliament]] protested against this subsidy, which they claimed provided unfair competition to their own [[Hydro Québec]] [[power company]].<ref>{{cite web|url=https://thenarwhal.ca/muskrat-falls-hydro-dam-trudeau-bailout/ |title=Trudeau offers $5.2 billion bailout for Newfoundland and Labrador’s beleaguered Muskrat Falls hydro dam|publisher=The Narwhal (Victoria, BC)|date=July 29, 2021 |access-date=Oct 16, 2022|quote =Meanwhile, the Bloc Quebecois is decidedly against the bailout. It sees the money as an unfair advantage to N.L., because Hydro-Quebec and Nalcor are both Crown corporations with significant hydropower competing for New England markets...“In launching this project, the Newfoundland government made no secret of the fact that its objective was to harm Quebec, bypass Quebec territory and compete with Hydro-Quebec on export markets. “By announcing such funding, the government of Justin Trudeau is directly attacking Hydro-Quebec, which has been trying for several years to increase its electricity sales in the United States, one of the markets targeted by Muskrat Falls,” the statement also reads. Hydro-Quebec declined comment.}}</ref> The [[Sheshatshiu Innu First Nation|Innu Nation]] protested the decision stating they had not been consulted.<ref>{{Cite web|date=Oct 14, 2021|title=Innu Nation repeatedly blindsided by Muskrat Falls announcements, letters show|url=https://www.cbc.ca/news/canada/newfoundland-labrador/innu-nation-not-tolerate-consultations-1.6209097|website=[[CBC News]]}}</ref> The Innu Nation also raised concerns about the compensation claimed by the [[Innu]] and how cost overruns may reduce the amount of Innu royalties received under the 2011 impact and benefits agreement.<ref>{{Cite web|date=Aug. 03, 2021|title=Muskrat Falls deal 'betrayed the Innu people,' says Innu Nation|url=https://www.cbc.ca/news/canada/newfoundland-labrador/innu-nation-muskrat-falls-agreement-1.6127949|website=[[CBC News]]}}</ref>


==See also==
==See also==

Revision as of 22:50, 3 June 2023

Muskrat Falls Generation Facility
LocationLabrador, Newfoundland and Labrador, Canada
Coordinates53°14′44″N 60°46′22″W / 53.24556°N 60.77278°W / 53.24556; -60.77278
Construction began2013 [1]
Opening dateSeptember 23, 2020
Construction cost$12.7 billion
Owner(s)Newfoundland and Labrador Hydro
Dam and spillways
Type of damRoller compacted concrete
ImpoundsChurchill River
Elevation at crest39.5 m[2]
Spillways2
Spillway type1 overflow spillway and 1 spillway with submerged radial gates[3]: 87–88 
Spillway capacity5930 m3/s [2]: 21 
Reservoir
Normal elevation39 m [2]: 20 
Power Station
Turbines4 x 206 MW Kaplan turbines [2]: 23 
Installed capacity824 MW[3]: 86 
Capacity factor62.3%
Annual generation4.5 TWh[3]: 86 

The Lower Churchill Project is an ongoing hydroelectric project in the Labrador region of the Province Newfoundland and Labrador, Canada, to develop the remaining 35 per cent of the Churchill River that was not developed by the Churchill Falls Generating Station. The station at Muskrat Falls will have a capacity of over 824 MW and provide 4.9 TWh of electricity per year.[4]

A $6.2 billion deal between Newfoundland and Labrador's Nalcor Energy and Halifax, Nova Scotia-based Emera to develop the project was announced in November 2010.[5] On November 30, 2012, a federal loan guarantee deal for financing of the project was signed by Prime Minister Stephen Harper, Newfoundland and Labrador Premier Kathy Dunderdale and Nova Scotia Premier Darrell Dexter.[6][7][8][9] On December 17, 2012, the provincial government announced project sanction.[10][11] Emera received approval to proceed with the Maritime Link from the Nova Scotia Utility and Review Board in 2013.[12] Financial close for the loan guarantee occurred in late 2013.[13] On September 23, 2020, the first unit at Muskrat Falls was synced to the electricity grid in Labrador. Power from the remaining three units was originally expected to come online in the fall of 2021.[14] However, there were delays in construction, including on the corresponding Labrador–Island Link which will transmit generated power to a converter outside St. John's.[15]

On June 23, 2021, Premier Andrew Furey announced Nalcor Energy would be dismantled and folded into Newfoundland and Labrador Hydro.[16]

In April 2023, Jennifer Williams, CEO of Newfoundland and Labrador Hydro, announced the completion of the final successful test of the 1100 km transmission link to Newfoundland. Commissioning by the federal government will be announced following the completion of paperwork. Originally approved in 2012 with an anticipated price tag of around $7.4 billion, the costs of the project had ballooned to more than $13 billion.[17]

Technical plan

Generation

Reservoir impoundment was completed in 2019 with the flooding of 41 km2 of land to create the 101 km2 reservoir. Containment is by a two-part concrete dam totalling 757 metres long. This will power an 834 MW generating station.[18]

Transmission

Power is transmitted to Newfoundland via a 2.1 billion dollar high-voltage direct current line. The total length is 1,100 km, of which 30 km are submarine power cables under the Strait of Belle Isle.[18] Construction began in 2014 and ended in 2018.[19]

Power is transmitted from Stephenville on Newfoundland to Nova Scotia via a 180 km sub-sea line to Point Aconi on Cape Breton Island. Construction is a 1.2 billion dollar joint venture between Nalcor and Emera.[18] The link came online in December 2017.[20]

Once on Newfoundland and the mainland of the Maritimes, power will be distributed via the existing grid. Emera hopes to sell surplus power via a proposed 563 km underwater transmission line from New Brunswick to Massachusetts.[21]

Environmental impact

In late 2006, Nalcor registered the generation components of the Lower Churchill Project, including both Gull Island and Muskrat Falls, for environmental assessment with the provincial and federal governments. The provincial and federal government agreed to a combined review process that would fulfill the requirements of both levels of government, resulting in the formation of a Joint Review Panel. In 2010, the focus shifted to Muskrat Falls only. The environmental assessment for the transmission lines was done separately and was conducted in 2013. Many Indigenous peoples had serious concerns about how the land and wildlife would be changed by the development. Negotiations between the Innu Nation and the provincial government began in 2006, resulting in the New Dawn (Tshash Petapen) Agreement, finalized in 2011.[22] This agreement included an Impacts and Benefits Agreement (IBA), a Redress Agreement related to damage caused by the Churchill Falls development, and an agreement in principle about the Innu Nation’s land claim. Upon the ratification of the New Dawn Agreement, the Innu Nation indicated that the project was acceptable to them.

In 2016, researchers from Harvard University found that methylmercury levels in fish would rise as a result of the project.[23][24] After protests led by Indigenous groups in Central Labrador in 2016, an agreement was reached by Labrador’s three Indigenous groups (Nunatsiavut Government, Innu Nation and the NunatuKavut Community Council) and the Government of Newfoundland and Labrador outlining the establishment of an independent committee to make recommendations on mitigating potential impacts of methylmercury on human health from the Lower Churchill Project at Muskrat Falls, Labrador.[25] In 2018, the committee recommended – among other things – wetland capping to stem the release of methylmercury.[26][27][28]

During the Muskrat Falls inquiry in 2019, it was revealed the provincial government wouldn’t be completing wetland capping at the Muskrat Falls reservoir as previously planned.[29][30] The $30 million designated for the capping was split up and offered to all three Indigenous governments, with the Innu Nation and NunatuKavut accepting.[31][32][33] Nalcor had applied for a permit in July 2018 to carry out the approximately 13 hectares of wetland capping – essentially pouring sand and stone over a small area of wetland near the reservoir – but the permit was never approved by the Department of Municipal Affairs and Environment.[34] Premier Dwight Ball later said wetland capping would have only decreased methylmercury levels by two per cent.[35][36]

Cost overruns and public inquiry

The project is more than $6 billion over budget,[37] and five years late as of 2022. Projected cost overruns exceeding 70% from $7.4 billion to $12.7 billion due to poor planning, lack of engineering experience, and related assumptions that were invalid, misleading or later turned out to be incorrect led Nalcor CEO Stan Marshall to say that the project was a boondoggle.[38][39]

In 2017, Premier Dwight Ball called a public inquiry into the project,[40] which took place between 2018 and 2020.[41] In the inquiry report, Commissioner Richard LeBlanc concluded the government failed its duty to residents by predetermining that the megaproject would proceed no matter what. In his report, LeBlanc concluded that the business case, which assumed the Muskrat Falls project was the lowest-cost power option, was “questionable.” LeBlanc said that the project’s economics were not sufficiently tested and that Nalcor failed to consider all potentially viable power options. LeBlanc said that Nalcor concealed information that could have undermined the business case for the project from the public and government.[42]

In July 2021, Prime Minister Justin Trudeau announced that the Government of Canada would provide the project with $5.2 billion of financial support to compensate for its large cost overrun (from $6.2 billion to over $13 billion) and to enable the province to maintain the price of power at a competitive rate (14.7 cents per kilowatt-hour).[43][44] The government of Quebec and Bloc Québécois Members of Parliament protested against this subsidy, which they claimed provided unfair competition to their own Hydro Québec power company.[45] The Innu Nation protested the decision stating they had not been consulted.[46] The Innu Nation also raised concerns about the compensation claimed by the Innu and how cost overruns may reduce the amount of Innu royalties received under the 2011 impact and benefits agreement.[47]

See also

References

  1. ^ "Construction schedule to first power" (JPG). Nalcor Energy. Retrieved 2014-07-26.
  2. ^ a b c d "Nalcor's submission to the Board of Commissioners" (PDF). Nalcor Energy. November 10, 2011. Retrieved December 27, 2011.
  3. ^ a b c Rae, P. (January 2012). "5". Report on Two Generation Expansion Alternatives for the Island Interconnected Electrical System (PDF) (Report). Vol. II. Winnipeg: Manitoba Hydro International. Retrieved 2014-07-26.
  4. ^ "Lower Churchill Project". Nalcor Energy. Retrieved June 8, 2013.
  5. ^ McCarthy, Shawn (18 November 2010). "Churchill hydro deal signals era of Atlantic co-operation – The Globe and Mail". The Globe and Mail. Toronto.
  6. ^ Bailey, Sue (November 30, 2012). "Harper signs loan guarantee deal for Muskrat Falls despite Quebec's outcry". Global News. Retrieved Nov 29, 2020.
  7. ^ "Terms of Muskrat Falls federal loan guarantee released". CBC News. Dec 4, 2012. Retrieved Nov 29, 2020.
  8. ^ "Harper to announce Muskrat Falls deal in Labrador". CBC News. Nov 29, 2012. Retrieved Nov 29, 2020.
  9. ^ "Harper 'reiterates support' for Muskrat Falls". CBC News. Sep 24, 2012. Retrieved Nov 29, 2020.
  10. ^ "Government of Newfoundland and Labrador Announces Sanction of the Muskrat Falls Development". Government of Newfoundland and Labrador. December 17, 2012. Retrieved Nov 29, 2020.
  11. ^ "$1.5B Maritime Link approved by Emera Inc". CBC News. Dec 18, 2012. Retrieved Nov 29, 2020.
  12. ^ "Maritime Link energy project approved by Nova Scotia's UARB". CBC News. Nov 29, 2013. Retrieved Nov 29, 2020.
  13. ^ "Speaking notes delivered December 10 by the Honourable Kathy Dunderdale". Government of Newfoundland and Labrador. December 17, 2012. Retrieved December 10, 2013.
  14. ^ "Muskrat Falls Generating Project". Nalcor Energy.{{cite web}}: CS1 maint: url-status (link)
  15. ^ Callahan, Brian (November 29, 2021). "Hydro Announces Completion of Muskrat Falls Generating Station". VOCM. Retrieved 24 January 2022.
  16. ^ "Nalcor Energy to be no more: Crown corporation being folded into N.L. Hydro". CBC News. June 23, 2021.
  17. ^ "Muskrat Falls hydroelectric project in N.L. considered commissioned: CEO". Globalnews.ca. April 12, 2023. Retrieved 2023-04-16.
  18. ^ a b c "Muskrat Falls Development Generation and Transmission". Government of Newfoundland and Labrador. Archived from the original on 26 December 2018. Retrieved 21 July 2019.
  19. ^ McKenzie-Sutter, Holly (June 27, 2018). "Transmission link between Labrador and Newfoundland energized as Muskrat Falls project nears completion". The Globe and Mail. Retrieved Nov 29, 2020.
  20. ^ "New power transmission towers connect Muskrat Falls, mainland Nova Scotia". Global News. August 2, 2018. Retrieved Nov 29, 2020.
  21. ^ Withers, Paul (Jan 12, 2017). "Halifax-based Emera makes plans for $2B Atlantic Link". CBC. Retrieved 21 July 2019.
  22. ^ "A New Dawn for the Labrador Innu". Government of Newfoundland and Labrador. November 18, 2011. Retrieved Nov 29, 2020.
  23. ^ Flowers, Bill (December 13, 2016). "Inadequate consultation on the Muskrat Falls project". Policy Options. Retrieved Nov 29, 2020.
  24. ^ Careen, Evan (November 20, 2016). "Methylmercury levels downstream from Muskrat Falls concern researcher". Saltwire Network. Retrieved Nov 29, 2020.
  25. ^ "Timeline - Independent Expert Advisory Committee". Independent Expert Advisory Committee. Retrieved 2018-10-30.
  26. ^ "Nunatsiavut president pleads with premier to pump the brakes on Muskrat Falls flooding". CBC News. Jul 22, 2019. Retrieved Nov 29, 2020.
  27. ^ Fitzpatrick, Ashley (April 8, 2019). "Advisory committee recommendations about Muskrat Falls deserve action: chair". The Telegram. Retrieved Nov 29, 2020.
  28. ^ Maher, David (June 7, 2019). "United Nations calls for methyl mercury mitigation at Muskrat Falls". The Telegram. Retrieved Nov 29, 2020.
  29. ^ Maher, David (July 4, 2019). "Newfoundland and Labrador government 'unintentionally' missed Muskrat Falls wetland capping deadline". The Telegram. Retrieved Nov 29, 2020.
  30. ^ Fitzpatrick, Ashley (June 20, 2019). "No time left for reservoir work prior to flooding, deputy minister tells Muskrat Falls Inquiry". The Telegram. Retrieved Nov 29, 2020.
  31. ^ "Methylmercury deal struck with 2 of 3 Labrador Indigenous groups". CBC News. Jul 23, 2019. Retrieved Nov 29, 2020.
  32. ^ White, Bailery (Jul 24, 2019). "Nalcor's $10M deal with NunatuKavut hammered out in a page and a half". CBC News. Retrieved Nov 29, 2020.
  33. ^ "Government skipped methylmercury deadline then offered 'hush money,' says Nunatsiavut president". CBC News. Aug 11, 2019. Retrieved Nov 29, 2020.
  34. ^ "Liberal minister dismisses call for investigation into Muskrat Falls wetland capping failure". CBC News. Aug 23, 2019. Retrieved Nov 29, 2020.
  35. ^ ""Last supper" held tonight by Muskrat Falls protestors". The Telegram. Aug 6, 2019. Retrieved Nov 29, 2020.
  36. ^ Roberts, Terry (Jun 27, 2019). "Too late to mitigate: Inquiry hears how wetland capping no longer a Muskrat option". CBC News. Retrieved Nov 29, 2020.
  37. ^ Cox, Sarah (May 16, 2019). "A reckoning for Muskrat Falls". The Narwhal. Retrieved 21 July 2019.
  38. ^ Sue Bailey (June 24, 2016). "'Project was not the right choice': Muskrat Falls estimate surpasses $11-billion". The Globe and Mail. Retrieved 2016-06-24.
  39. ^ Roberts, Terry (Apr 19, 2019). "Muskrat Falls: A story of unchecked oilmen and their boondoggle hydro project". CBC News. Retrieved Nov 29, 2020.
  40. ^ Vaughan, Andrew (September 29, 2017). "Newfoundland Premier announces inquiry into Muskrat Falls project". The Globe and Mail. Retrieved Nov 29, 2020.
  41. ^ "Premier Ball Announces Muskrat Falls Public Inquiry". Government of Newfoundland and Labrador. November 20, 2017. Retrieved Nov 29, 2020.
  42. ^ McKenzie-Sutter, Holly (March 10, 2020). "Final report from Muskrat Falls inquiry released to the public". The Globe and Mail. Retrieved Nov 29, 2020.
  43. ^ "$5.2B deal reached between feds, N.L. government to stave off skyrocketing power bills". CBC News. July 28, 2021.
  44. ^ "Ottawa to give N.L. billions of dollars to offset Muskrat Falls costs". CBC News. July 27, 2021.
  45. ^ "Trudeau offers $5.2 billion bailout for Newfoundland and Labrador's beleaguered Muskrat Falls hydro dam". The Narwhal (Victoria, BC). July 29, 2021. Retrieved Oct 16, 2022. Meanwhile, the Bloc Quebecois is decidedly against the bailout. It sees the money as an unfair advantage to N.L., because Hydro-Quebec and Nalcor are both Crown corporations with significant hydropower competing for New England markets..."In launching this project, the Newfoundland government made no secret of the fact that its objective was to harm Quebec, bypass Quebec territory and compete with Hydro-Quebec on export markets. "By announcing such funding, the government of Justin Trudeau is directly attacking Hydro-Quebec, which has been trying for several years to increase its electricity sales in the United States, one of the markets targeted by Muskrat Falls," the statement also reads. Hydro-Quebec declined comment.
  46. ^ "Innu Nation repeatedly blindsided by Muskrat Falls announcements, letters show". CBC News. Oct 14, 2021.
  47. ^ "Muskrat Falls deal 'betrayed the Innu people,' says Innu Nation". CBC News. Aug. 03, 2021. {{cite web}}: Check date values in: |date= (help)