Jump to content

Budgeted cost of work performed: Difference between revisions

From Wikipedia, the free encyclopedia
Content deleted Content added
Tomdobb (talk | contribs)
mNo edit summary
SmackBot (talk | contribs)
m Date maintenance tags and general fixes
Line 1: Line 1:
{{Cleanup|date=February 2009}}
{{improve}}


'''Budgeted Cost of Work Performed''' (BCWP), or "Earned Value" (EV), in [[project management]] is the budgeted cost of work that has actually been performed in carrying out a scheduled task during a specific time period<ref>Project Management Institute (1998) [[A Guide to the Project Management Body of Knowledge]] - Third Edition 2004. ISBN 1-930699-45-X</ref>. The term is connected with [[Earned value management]] and here it is different from:
'''Budgeted Cost of Work Performed''' (BCWP), or "Earned Value" (EV), in [[project management]] is the budgeted cost of work that has actually been performed in carrying out a scheduled task during a specific time period<ref>Project Management Institute (1998) [[A Guide to the Project Management Body of Knowledge]] - Third Edition 2004. ISBN 1-930699-45-X</ref>. The term is connected with [[Earned value management]] and here it is different from:
Line 8: Line 8:
As example of the difference assume that a schedule contains:
As example of the difference assume that a schedule contains:
* a task "Test hardware" that is budgeted to cost $1000 to perform, and
* a task "Test hardware" that is budgeted to cost $1000 to perform, and
* is expected to begin at the start of January 1st and
* is expected to begin at the start of January 1 and
* complete at the end of January 10th.
* complete at the end of January 10.
At the end of January 5th, the work is scheduled to be 50% complete (5 days of the scheduled 10 days). So, at the end of January 5th,
At the end of January 5, the work is scheduled to be 50% complete (5 days of the scheduled 10 days). So, at the end of January 5,
* the BCWS is $1000 (the budgeted cost) times 50% (the scheduled completion percentage), or $500.
* the BCWS is $1000 (the budgeted cost) times 50% (the scheduled completion percentage), or $500.


Suppose that by the end of January 5th, the work is actually only 30% complete. In this case,
Suppose that by the end of January 5, the work is actually only 30% complete. In this case,
* the BCWP would be $1000 (budgeted cost) times 30% (the actual completion percentage), or $300.
* the BCWP would be $1000 (budgeted cost) times 30% (the actual completion percentage), or $300.


Also, suppose that to reach the 30% complete level at the end of January 5th, $250 was actually spent.
Also, suppose that to reach the 30% complete level at the end of January 5, $250 was actually spent.
* Then, the ACWP would be $250.
* Then, the ACWP would be $250.


== References ==
== References ==
{{reflist}}
{{reflist}}

{{Business-stub}}


[[Category:Project management]]
[[Category:Project management]]
[[Category:Budgets|Cost of work scheduled]]
[[Category:Budgets|Cost of work scheduled]]


{{Business-stub}}

Revision as of 01:40, 5 February 2009

Budgeted Cost of Work Performed (BCWP), or "Earned Value" (EV), in project management is the budgeted cost of work that has actually been performed in carrying out a scheduled task during a specific time period[1]. The term is connected with Earned value management and here it is different from:

  • Budgeted Cost of Work Scheduled (BCWS) : the approved budget that has been allocated to complete a scheduled task during a specific time period.
  • Actual Cost of Work Performed (ACWP) : the actual cost that has been spent, rather than the budgeted cost.

As example of the difference assume that a schedule contains:

  • a task "Test hardware" that is budgeted to cost $1000 to perform, and
  • is expected to begin at the start of January 1 and
  • complete at the end of January 10.

At the end of January 5, the work is scheduled to be 50% complete (5 days of the scheduled 10 days). So, at the end of January 5,

  • the BCWS is $1000 (the budgeted cost) times 50% (the scheduled completion percentage), or $500.

Suppose that by the end of January 5, the work is actually only 30% complete. In this case,

  • the BCWP would be $1000 (budgeted cost) times 30% (the actual completion percentage), or $300.

Also, suppose that to reach the 30% complete level at the end of January 5, $250 was actually spent.

  • Then, the ACWP would be $250.

References

  1. ^ Project Management Institute (1998) A Guide to the Project Management Body of Knowledge - Third Edition 2004. ISBN 1-930699-45-X