Jump to content

Rihand Thermal Power Station: Difference between revisions

Coordinates: 24°01′36″N 82°47′24″E / 24.0267°N 82.79°E / 24.0267; 82.79
From Wikipedia, the free encyclopedia
Content deleted Content added
Pskale (talk | contribs)
Fixed a minor typing mistake
Line 61: Line 61:
! Stage !! Unit Number !! Installed Capacity ([[Watt#Megawatt|MW]]) !! Date of Comisioning !! Status
! Stage !! Unit Number !! Installed Capacity ([[Watt#Megawatt|MW]]) !! Date of Comisioning !! Status
|-
|-
| First || 1 || 500 || March, 1988 || Running
| 1st || 1 || 500 || 1988 March || Running
|-
|-
| First || 2 || 500 || July, 1989 || Running
| 1st || 2 || 500 || 1989 July || Running
|-
|-
| Second || 3 || 500 || January, 2005 || Running
| 2nd || 3 || 500 || 2005 January || Running
|-
|-
| Second || 4 || 500 || September, 2005 || Running
| 2nd || 4 || 500 || 2005 September || Running
|-
|-
| Third || 5 || 500 || May 25, 2012 at 02:29 Hrs <ref>{{cite web|url=http://www.bseindia.com/stockinfo/anndet.aspx?newsid=14DB29A5-021E-4E4C-9F9E-C4FB7F650DE7&flag=I&type=A&scrip_CD=532555|title=Unit # 5 of 500 MW of Rihand Super Thermal Power Project commissioned|publisher=National Thermal Power Corporation via Bombay Stock Exchange.}}</ref> || Running
| 3rd || 5 || 500 || 2012 May <ref>{{cite web|url=http://www.bseindia.com/stockinfo/anndet.aspx?newsid=14DB29A5-021E-4E4C-9F9E-C4FB7F650DE7&flag=I&type=A&scrip_CD=532555|title=Unit # 5 of 500 MW of Rihand Super Thermal Power Project commissioned|publisher=National Thermal Power Corporation via Bombay Stock Exchange.}}</ref> || Running
|-
|-
| Third || 6 || 500 || ---- || Under Commissioning
| 3rd || 6 || 500 || ---- || Under Commissioning
|-
|-
|}
|}

Revision as of 10:56, 26 June 2012

Rihand
Thermal Power Station
Map
CountryIndia
Coordinates24°01′36″N 82°47′24″E / 24.0267°N 82.79°E / 24.0267; 82.79
StatusOperational
Commission date1988
OwnerNTPC
Power generation
Nameplate capacity
  • 3,000 MW
External links
Websitehttps://www.ntpc.co.in/

Rihand Thermal Power Station is located at Rihandnagar in Uttar Pradesh. The power plant is one of the coal based power plants of NTPC

Power plant

Rihand Thermal Power Station has an installed capacity of 2000 MW. The First unit was commissioned in March 1988. The coal for the plant is derived from Amlori and Dudhichua mines. The water source is from Rihand Reservoir which is constructed on sone river.[1].

Installed capacity

Stage Unit Number Installed Capacity (MW) Date of Comisioning Status
1st 1 500 1988 March Running
1st 2 500 1989 July Running
2nd 3 500 2005 January Running
2nd 4 500 2005 September Running
3rd 5 500 2012 May [2] Running
3rd 6 500 ---- Under Commissioning

See also

{{{inline}}}

References

  1. ^ "Rihand Thermal Power Station". National Thermal Power Corporation.
  2. ^ "Unit # 5 of 500 MW of Rihand Super Thermal Power Project commissioned". National Thermal Power Corporation via Bombay Stock Exchange.