Nanning Metro
File:Nanning Rail Transit.png
Overview
LocaleNanning, Guangxi, China
Transit typeRapid Transit
Number of lines4
Number of stations66
Daily ridership0.5852 million (2018 daily avg.)[1] 1.3957 million (1 January 2021 record)[2]
Annual ridership0.214 billion (2018)
Websitehttp://www.nngdjt.com/
Operation
Began operationJune 28, 2016; 8 years ago (2016-06-28)
Operator(s)Nanning Rail Transport Limited
Number of vehicles66 (2019)
Technical
System length81.0 km (50.3 mi)
Track gauge1,435 mm (4 ft 8 1⁄2 in)
System map


Nanning Rail Transit
Chinese name
Simplified Chinese南宁轨道交通
Traditional Chinese南寧軌道交通
Transcriptions
Standard Mandarin
Hanyu PinyinNánníng Guǐdào Jiāotōng
Alternative Chinese name
Simplified Chinese南宁地铁
Traditional Chinese南寧地鐵
Transcriptions
Standard Mandarin
Hanyu PinyinNánníng Dìtiě
Zhuang name
ZhuangNanzningz Didez

Nanning Metro or Nanning Nanning Rail Transit (NNRT) is a rapid transit system in Nanning, the capital of Guangxi Zhuang Autonomous Region. Line 1 officially started construction on December 29, 2011.[3] The first 11.2 km section, from Nanhu to Nanning East railway station, began operation June 28, 2016.[4] The line opened fully on December 28, 2016. It is 32.1 km long, with 25 stations.[3][5] Line 2 started construction in 2012 and was completed on December 28, 2017.[6][7] Currently, Lines 3, 4, 5 and an extension of Line 2 are under construction. It is planned that by 2021 there will be four vertical and four horizontal lines totaling 252 km of subway. The system is projected to carry over 5 million passengers per day.[3][8]

Lines in operation

Line Terminals
(District)
Commencement Newest
Extension
Length
km
Stations
 1  Shibu
(Xixiangtang)
Nanning East railway station
(Qingxiu)
2016 2016 32.1 25
 2  Xijin
(Xixiangtang)
Tanze
(Liangqing)
2017 2020 27.3 23
 3  Keyuan Dadao
(Xixiangtang)
Pingliang Overpass
(Liangqing)
2019 27.9 23
 4  Hongyunlu Lentangcun 2020 20.7 16
Total 108.0 84

Future Expansion

Planned opening date Route Name Terminals Length (km) Stations Status
2021  5  Phase I Guokai Dadao Jinqiao Coach Station 20.38 km 17 [9]

Network Map

Map


See also

References

  1. ^ http://3g.nnwb.com/html/2019-08/25/content_370171.htm
  2. ^ http://www.gx.xinhuanet.com/newscenter/2021-01/02/c_1126938153.htm
  3. ^ a b c 罗宁 (2011-12-29). "南宁轨道交通一号线工程全线开工". 南宁新闻网 (in Chinese). 人民网. Retrieved 2012-01-01.
  4. ^ http://www.urbanrail.net/as/cn/nanning/nanning.htm
  5. ^ "南宁轨道交通1号线全线开通试运营-广西新闻网". www.gxnews.com.cn. Retrieved 2016-12-28.
  6. ^ "南宁轨道交通2号线预计年底开工2017年建成 连接玉洞西津". People's Daily. 2013-01-18. Archived from the original on 2013-08-01.
  7. ^ chinanews. "南宁地铁2号线开通试运营 轨道交通建成"十字网"-中新网". www.chinanews.com. Retrieved 2017-12-29.
  8. ^ "2021年南宁将开通5条地铁线路 轨道交通连线成网". People's Daily. 2017-12-28. Archived from the original on 2017-12-29.
  9. ^ "南宁市城市轨道交通 5 号线一期工程(那洪~金桥客运站)环境影响评价公众参与第二次公示" (PDF). www.crfsdi.com.cn. 2016-10-12. Archived from the original (PDF) on 2016-10-12. Retrieved 2019-01-13.