Red Line (Tel Aviv Light Rail)
Red Line | |
---|---|
Overview | |
Locale | Tel Aviv, Petah Tikva, Bnei Brak, Ramat Gan, Bat Yam |
Termini |
|
Stations | 34 |
Website | www |
Service | |
Type | Light rail |
System | Tel Aviv Light Rail |
Operator(s) | NTA |
Depot(s) | Kiryat Aryeh depot |
Daily ridership | ~240,000 (projected) |
History | |
Opened | August 18, 2023 |
Technical | |
Line length | 24 km (15 mi) |
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge |
Electrification | 1500 V DC OHLE |
Operating speed | 50 km/h (31 mph) in Street Level 70 km/h (43 mph) Underground |
The Red Line is the first section of a light rail system in the Tel Aviv metropolitan area, known as the Tel Aviv Light Rail. The line runs from Bat Yam in the south to Petah Tikva in the northeast with a significant portion of it underground. The total cost of the red line is estimated at NIS 11 billion or, approximately US$3 billion. Construction began in 2011, with the testing phase of the line beginning only a decade later, in 2021.[1] After numerous delays concerning the security and safety during the testing phase, the train was suddenly stopping at certain points. The mayor of Petah Tikva then surprisingly announced that the line would open in July 2023.[2] Days later, the line was approved by all security factors eventually opened on August 18 2023[3] with a whopping 100,000+ passengers on the first day over just 8 hours of operation.[4]
Route
The Red Line has a total of 34 stations. It will start at Petah Tikva's Central Bus Station, east of Tel Aviv and follow Jabotinsky Road (Route 481) westwards at street level. At the point where Jabotinsky Road and Highway 4 intersect the line drops into a tunnel for 11 km (6.8 mi)[5] and emerges to street level again just before Jaffa, where it turns southwards towards Bat Yam. The underground section includes 10 stations, including an interchange with Israel Railways services at Tel Aviv Central Railway Station and the nearby 2000 Terminal. A maintenance depot, connected via a branch line and tunnel to the main section of the line, was constructed in Kiryat Aryeh, across from the existing Kiryat Arye suburban railway station. The branch line includes two passenger stations, at Em HaMoshavot Road and an interchange station at the Kiryat Arye railway station.
A planned southern extension will add 2.8 km (1.7 mi) into the city of Rishon LeZion and three intermediate stops and an inter-modal terminus which will serve as connection with Israel Railways' Rishon LeZion Moshe Dayan Railway Station and the projected Green Line.[6]
Operations
The Red Line operates between the hours 5:00 AM with the last train departing at 0:30 AM the next day on Sunday to Thursday. On Friday, the last train departs 3 hours before Shabbat, and on Shabbat, there is no service at all on the line.
The price for a single ride is 5.50 NIS. For journeys beyond 15km, the price for a single ride jumps to 12 NIS.
There are 45 trains on the line during operating times each with 2 carriages and with a maximum capacity of 450 passengers per train.[7]
Waiting times in peak hours are approximately 3 minutes and off-peak hours the frequency will be 6 minutes per train. However, the frequency of the trains should increase as time goes by.[8]
Operator
In December 2006, the concession to build and operate the Red Line was awarded to the Metropolitan Transportation Solution (MTS) Consortium, which consisted of Africa Israel Investments, China Civil Engineering Construction Corporation (CCECC), Soares da Costa (Portugal), the Egged Bus Cooperative, Siemens, and the Dutch transportation company HTM.
In February 2007, the NIS 7.1 billion concession was a Build Operate Transfer (BOT) contract, the biggest private sector contract ever tendered in Israel's history. MTS's bid was just NIS 400 million under that of rival Metrorail, who bid NIS 7.5 billion.[9]
Financing difficulties
In February 2007, the BOT agreement with the MTS consortium was signed and construction was to start a year later, in February 2008.[9] However, the consortium was unable to secure the necessary financing and was given several extensions to the agreed timetable. The difficulties raising the funding was attributed to the global financial crisis and specifically to the financial problems at Africa Israel Investments Group.[10]
In November 2009, the Israeli government announced that it was considering canceling the agreement with the consortium and granted another extension until March 2010. It was announced that if funding is not secured by then, the government will consider other options for financing the railway, including the option of using public instead of private funding for the project. The deadline was then extended again to summer 2010 and in August the government, after extensive negotiations with MTS failed, finally canceled the MTS concession, though MTS indicated it would appeal the government's decision in arbitration proceeding.[citation needed]
NTA takes over
Following the cancellation of the MTS contract, the government announced that it would fund the construction directly from the Treasury and that NTA would manage subsequent phases of construction. As a result, NTA published a tender for the design of multiple launching shafts for the TBMs that would dig the 11 km of tunnels for the railway.
In March 2011, the shafts' construction tender was published as well, in addition to a tender for the design of the Kiryat Aryeh depot. The anticipated overall completion date of the railway was 31 December 2017.[11] On December 20, 2010, the transfer of the entire project's management to NTA was approved by the project's arbitrators with MTS. On January 12, 2012, NTA published a pre-qualify (PQ) bid for the design-build contract for excavating the Red and Green lines' tunnels to be performed by several TBMs operating simultaneously.
From October 2021, Egged has been awarded the tender to operate and maintain the Tel Aviv Red Line by the NTA Metropolitan Mass Transit System Ltd. tenders committee. The winning bid was from the Tevel consortium controlled by Egged (51%) with Chinese companies Shenzhen Metro (30%) and CCECC (19%). The tender win is subject to approval by the Israel Antitrust Authority.
Construction
The Red Line is the second underground service in Israel, after the Carmelit, in Haifa. The line is 24 km (15 mi) in length, with 34 stops, of which 10 are underground. The underground stations are equipped with platform screen doors[6] and also trains in the underground section are operated via an automatic train operation system.[12]
Preparatory works
Initial preparatory works began in 2007. NTA, the Government body responsible for the mass-transit development in the Tel Aviv region has spent several years performing utility relocation and right-of-way clearing for the railway. The bulk of the work however, including underground excavation, is to be carried out by the operator.
On April 10, 2008, works started on the conversion of part of the Jabotinsky Rd. in Petah Tikva into a sunken passage below Kaplan St.[13]
As part of the preparatory works for the line, the main entrance to the Batei HaOsef museum in south Tel Aviv was cleared and relocated. The Bank HaPoalim branch on Herzl Street in the same area was also demolished.[14]
TBM Shafts
In September 2011, work started on constructing 3 launching shafts for the TBMs[15]
- Herzl Street shaft - located at the point where a cut and cover section ends and the tunneled section starts, used to launch TBMs in an easterly direction.
- Galei Gil car park shaft - located near the Ayalon Highway - used to launch TBMs in both easterly and westerly directions.
- Em HaMoshavot shaft - located near Highway 4 in Bnei Brak, used to launch TBMs in a westerly direction.
Tunnelling Works
In May 2015, the companies Solel Boneh and China Railway Tunnel Group won the 2.9 Billion NIS tender to build two 5-kilometre (3.1 mi) tunnels and 6 underground stations in the western section of the Tel Aviv light rail's red line.[16]
In June 2015, the companies Danya Cebus and China Civil Engineering Construction Corporation (CCECC) won the 700 Million NIS tender to build underground Carlebach station of the Tel Aviv light rail's red line.
By February 2017, most of the stations on the Red Line were already under construction.[citation needed]
Testing Phase
In 2021, the testing phase of the Red Line started after construction ended. The first trains started driving across the tracks.[17]
During this phase, many problems involving the brakes of the trains suddenly stopping in the middle of the tracks became the center of attention in this phase. The companies were desperately trying to fix this major issue that lead to severe delays to the lines opening date.[18]
In 2023, the issue was fixed and the line was approved by all security factors which lead to its opening in August.
Extensions
On December 5, 2022, the Ministry of Transportation allocated approximately NIS 100 million for the extension of the Red Line. This is for the purpose of detailed planning of a route from Bat Yam to the Rishon LeZion - Moshe Dayan train station.[19] The planning extended the line by 2.5 kilometers, and included the construction of four new stations: Menachem Begin station, Koresh station, Rehavam Zaevi station and Shimon Israel station, which will be built near the Moshe Dayan interchange.
Rolling stock
The Red Line trams are manufactured by CRRC Changchun Railway Vehicle Company. One LRV include 5 modules, The configuration is Mc1+F1+Tp+F2+Msc1. Two vehicles are combined as one trainset for operation. The vehicle comply with ISO, EN and Israel standards.
See also
References
- ^ "Tel Aviv Light Rail Completes First Test Drive". Haaretz. Retrieved 2023-07-03.
- ^ "קרב גרסאות בין ראש עיריית פתח תקווה לחברת נת"ע: מתי ייפתח הקו האדום של הרכבת הקלה? | ישראל היום". www.israelhayom.co.il. 2023-06-22. Retrieved 2023-07-03.
- ^ "Tel Aviv light rail approved to begin operating on August 18". The Jerusalem Post. 2023-08-04. Retrieved 2023-08-04.
- ^ "'We waited a long time for this': Tel Aviv light rail sets off after years of delays". The Times of Israel. 2023-08-18. Retrieved 2023-08-18.
- ^ "Tel Aviv Red Line tunnelling begins". Railway Gazette International. 20 February 2017. Retrieved 8 December 2020.
- ^ a b RFI - Preliminary and Final Design of 10 Underground Stations of the Red Line, NTA Site, 15 November 2010
- ^ "Israel's New Light Rail Line". Haaretz. Retrieved 2023-08-19.
- ^ "Tel Aviv light rail will launch at lower speed, frequency". Globes. 2023-02-27. Retrieved 2023-08-19.
- ^ a b "Tel Aviv contract signed amid legal disputes.(Transit News)", International Railway Journal, February 1, 2007, retrieved 2009-11-19
- ^ Baron, Lior (2009-11-16), "Tel Aviv light rail co wants talks, not hearing MTS: A hearing is unacceptable under the terms of the franchise contract", Globes, retrieved 2009-11-19
- ^ Avi Bar-Eli (2010-09-24), "Back on track? / State issues new tender for Tel Aviv light rail", TheMarker, retrieved 2010-10-25
- ^ RFI for Acquisition and Maintenance of the Light Rail Vehicles Fleet, NTA Site, 17 November 2010
- ^ Rothschild, Walter (September 28, 2008). "Light Rail Projects – Tel Aviv – Cutting" (PDF). HaRakevet (82): 10. Retrieved 2010-08-28.
- ^ Rothschild, Walter (June 2008). "Light Rail – Tel Aviv" (PDF). HaRakevet (81): 7. Retrieved 2010-08-28.
- ^ Tel Aviv light rail to be built underground, Globes 12 Feb 2012
- ^ "Arison, Chinese co win TA light rail underground tender - Globes". 19 May 2015.
- ^ Zagrizak, Asaf (2021-06-10). "Light rail line in central Israel launches first public test drive". Ynetnews. Retrieved 2023-08-19.
- ^ Burroughs, David (2022-09-07). "Tel Aviv Red Line opening could be delayed as issues mount". International Railway Journal. Retrieved 2023-08-19.
- ^ "מסלול הרכבת הקלה מתארך לראשון לציון וגבעת שמואל | כלכליסט". calcalist (in Hebrew). 2022-12-05. Retrieved 2023-08-19.