Changzhou Metro 常州轨道交通
Overview
LocaleChangzhou, Jiangsu, China
Transit typeRapid transit
Number of lines2
Number of stations44
Websitewww.czmetro.net.cn
Operation
Began operation21 September 2019; 5 years ago (2019-09-21)[1]
Technical
System length54.03 km (33.57 mi)

The Changzhou Metro is a rapid transit system in Changzhou, Jiangsu province, China. The system started operation on 21 September 2019, with the opening of its first line, Line 1.[1]

Construction of Line 1 began on 28 October 2014. The line opened on 21 September 2019.[1]

Lines in operation

Line Terminals
(District)
Commencement Length
km
Stations
 1  Template:ChangzhouM stations
(Xinbei)
Template:ChangzhouM stations
(Wujin)
21 September 2019 34.24[2] 29
 2  Template:ChangzhouM stations
(Zhonglou)
Template:ChangzhouM stations
(Wujin)
28 June 2021 19.79[3] 15
Total 54.03 44

Line 1

Line 1 started operation on 21 September 2019.[1] Construction for Line 1 began on 28 October 2014. The first phase runs from Template:ChangzhouM stations (森林公园) in the north to Template:ChangzhouM stations (南夏墅) in the south. It is 34.24 kilometres (21.28 mi)[2] in length with 29 stations, including 27 underground and 2 elevated. The line will be extended North for 3.5 km and South for 3.2 km.[4]

Line 2

Construction for Line 2 began on 13 February 2017.[5] It is 19.79 kilometres (12.30 mi)[3][5] in length with 15 stations, from Template:ChangzhouM stations to Template:ChangzhouM stations.[5] It was opened on 28 June 2021.[3]

Planned

As of June 2021 no line is under construction.

According to the "Changzhou Urban Rail Transit Construction Plan (2011~2018)", the urban rail transit network of Changzhou City planned by 2050 consists of 12 lines (7 urban lines and 5 suburban lines) with a total length of about 330 kilometers and 209 stations, including 15 interchange stations. The line network density in the core area is 1.12 km/km2, and the line network density in the central urban area is 0.19 km/km2.[6]

Short term

Line Construction start Estimate opening Section Stations Length References
 1  (North ext.) Forest Park - Chunjiang 2 3.5 [4]
 1  (South ext.) Nanxiashu - Changzhou South railway station 2 3.2 [4]
 2  (West ext.) Hexi - Qingfeng Park 7 8.6 [4]
 2  (East ext.) Wuyi Lu - Qishuyan railway station 4 5.0 [4]
 5  Lanyuewan - Dongqing 25 31.4 [4]
 6  Wujin Yanjiang railway station - Jianye Lu 25 34.0 [4]

Long term

The network is planned to comprise 7 lines with a total length of about 292 kilometres (181 mi) in long term plan.[7]

Fares

Changzhou Metro has a starting price of 2 yuan, a starting mileage of 5 kilometers, and an upgrade mileage of "5, 5, 7, 7, 9" kilometers, and an increase of 1 yuan for each level. Namely: the fare of less than 5 kilometers (inclusive) is 2 yuan, the fare of 5-10 (inclusive) kilometers is 3 yuan, the fare of 10-15 (inclusive) kilometers is 4 yuan, and the fare is 15-22 (inclusive) kilometers. 5 yuan, 6 yuan fare for 22-29 (inclusive) kilometers, an increase of 1 yuan for every 9 kilometers above 29 kilometers.[8]

Every year, April 22 (Earth Day), June 5 (World Environment Day), and September 22 (World Car-Free Day) are free travel days, and citizens can travel for free.

Trains

The models selected for the first phase were manufactured by Nanjing CRRC Puzhen Urban Rail Vehicle Co., Ltd. The trains used by Changzhou Rail Transit Line 1 are Type B cars. Each train is composed of 4 moving, 2 towing and 6 sections. The first phase of the project is equipped with 36 trains. There are 6 cars in the whole car with a total length of about 120 meters and the widest part of the car body. Up to 2.9 meters, the maximum operating speed is 80 km/h, each car has 4 pairs of driving doors on each side, the whole train has 48 pairs of driving doors, the width of the doors is 1.3 meters, and the whole train has 264 seats. The maximum passenger capacity is 2062 people. At the same time, the train adopts lightweight aluminum alloy material with a service life of 30 years. It has the characteristics of light weight, energy saving, consumption reduction, environmental protection, excellent fire resistance and arc resistance, corrosion resistance, and ease of processing, manufacturing, and maintenance. [9]

Network Map

Map


References

  1. ^ a b c d "常州地铁1号线今日正式开通初期运营". 2019-09-21.
  2. ^ a b "定了!常州市轨道交通1号线本周六上午9:30开通". 2019-09-18. Archived from the original on 2019-09-21. Retrieved 2019-09-18.
  3. ^ a b c "常州地铁二号线开通 "地铁时代"跨入"换乘时代"". 2021-06-23.
  4. ^ a b c d e f g "【征询】常州市城市轨道交通第二期建设规划(2020-2026年)环评公众意见征询". 2020-03-19.
  5. ^ a b c "常州地铁2号线一期工程全面开工 2020年试运营". 2017-02-13. Archived from the original on 2019-11-01. Retrieved 2019-11-06.
  6. ^ "常州市城市轨道交通近期建设规划通过批准". 2012-05-31.
  7. ^ "齐家滨陈金虎调研我市历史文化名城和交通建设情况". 2020-01-06.
  8. ^ "市发展改革委 市交通局关于核定常州市轨道交通(地铁)票价的通知". 2019-08-16.
  9. ^ "来了,常州地铁1号线首列车亮相". 2018-05-29.