Finnish railway signalling
The signalling system used on the railway network in Finland comprises color-light signals and fixed signs, used together with the Automatic Train Control system ATP-VR/RHK (an EBICAB 900 system better known as JKV, Template:Lang-fi).
Main signals
The main signal can have any of the following aspects:
Aspect | Meaning | Old system (Helsinki area) | |
---|---|---|---|
Stop | The signal must not be passed. | ||
Proceed | The signal may be passed with the maximum allowed speed. | ||
Proceed 35 | The signal may be passed and the maximum speed of 35 km/h (22 mph) is in effect from the next switch, which may lead to the diverging route. An ATC cab display may authorize a higher speed, typically 80 km/h (50 mph). The speed is in effect until the next main signal or after leaving the station area. The route may also lead to an occupied track section, but only if the driver has received a preliminary announcement. |
If a main signal doesn't protect any switches or the speed restriction on a diverging route is the same as straight route, the signal doesn't need to show the Proceed 35 aspect and therefore the yellow bottom light may be absent. The two lamp version of the old system has the lights reversed, i.e. red at the top and green at the bottom.
Distant signals
The distant signal is located at least 1,200 metres (3,900 ft) before the main signal. It may also be located in the same post with a main signal, below it. In this combined arrangement, whenever the main signal shows a stop aspect, the distant signal doesn't show any aspect at all.
A distant signal can have any of the following aspects:
Aspect | Meaning | Old system (Helsinki area) | |
---|---|---|---|
Expect Stop | The next signal shows the Stop aspect. The train route may also be set to a track section without further signals, e.g. toward unsignalled line or a buffer stop. | File:Opastin vanha odota seis.svg | |
Expect 35 | The next main signal shows the Proceed 35 aspect. | ||
Expect Proceed | The next signal shows the aspect Proceed. |
Note: Although the green light of the old system distant signal used in Helsinki area is named Expect Proceed aspect, the next main signal may in fact be showing the Proceed 35 aspect. Therefore, the driver has to act as if the signal aspect is indeed Expect 35.
Block signals
A block signal can show any of the following three aspects:
Block signals are being replaced by combinations of main and distant signals, and no new block signals will be installed.
Dwarf signals
A dwarf signal is used for controlling shunting movements. It can have any of the following aspects:
A dwarf signal may also be placed in conjunction with a main signal. If the main signal shows any other aspect than Stop, the dwarf signal shows the Proceed with caution aspect.
Bridge signals
Bridge signals are small signals used to display the orientation of a moveable bridge. They can have any of the following aspects:
Repeaters
Repeaters are sometimes used to repeat the aspect of the main signal in the Helsinki area in places where the main signal is not clearly visible.
Aspect | Meaning |
---|---|
The main signal is showing the Stop aspect. | |
The main signal is showing some Proceed aspect. The train can be moved to the main signal. |
Helsinki Metro
The Helsinki Metro signals differ from those used by the railways.
Main signals
Some aspects may be shown using a signal with only three lights, pictured on the right.
Distant signals
Aspect | Meaning | |
Expect other than Proceed | The next main signal is showing one of the aspects Stop, Proceed 35 or Coupling. | |
Expect Proceed | The next main signal is showing the Proceed aspect. |
References
- "RVI/1091/412/2009 Rautatiejärjestelmän opasteista, opastimista ja liikennöintiin liittyvistä merkeistä" (in Finnish and Swedish). Finnish Transport Safety Agency. 28 December 2009. Retrieved 2 May 2011.
External links
Media related to Railway signals in Finland at Wikimedia Commons