Hallandsås Tunnel
The Hallandsås Tunnel (Template:Lang-sv), also known as the Hallandsås Ridge Tunnel or Scanlink, is a railway tunnel under construction in Sweden. The planned length is 8.5 km (5.3 miles). It will be located on the Västkustbanan (West Coast Railway), on the section between Ängelholm and Halmstad in southwestern Sweden. When finished, it will enhance the connection between the cities of Gothenburg, Sweden and Copenhagen, Denmark.
In the bigger project on rebuilding the whole west coast line to dual track, the singe-track stretch over the ridge was both too curvy and steep to allow for easy conversion and still allow for high-speed passenger trains and heavy freight trains. The time saving for passenger trains will be about 10 minutes with the new tunnel, but more significantly the capacity will increase from 4 to 24 trains per hour over the ridge. Today, the ridge is a bottle neck and the high-speed train service between Gothenburg/Oslo and Malmö, as well as most freight trains do a long detour along the Halmstad-Hässleholm railway (which is also somewhat too steep for efficient freight traffic) and on the congested railway Hässleholm-Malmö. The tunnel project was conceived by the European Round Table of Industrialists and the Swedish Railway Administration in the 1980s.
Construction
The construction began in 1992, and the traffic opening was originally planned for 1995. However, construction was plagued by major difficulties concerning large amounts of water seeping in from surrounding rock. Only a small fraction of this water leakage had been foreseen. Additionally, a scandal broke out when it was learned that a poisonous sealing compound called "Rhoca-Gil" was used during construction. This substance was linked to the death of nearby livestock. Rhoca-Gil contains acrylamide, a toxic chemical that is mutagenic and possibly carcinogenic. The main contractor, Skanska, took no special precautions for the sealant. Also, it did not tell its own workers or the local population of the risks. By October 1997, local cattle and fish started dying. In addition, workers were becoming ill. The local press started an investigation. After tests were done showing the high levels of acrylamide contamination, the site was declared a high risk zone and the sale of agricultural products from the region was banned. The main contractor, Skanska, along with Rhone-Poulenc and Swedish Railways all had criminal charges brought against them. Some senior executives resigned as a result. Construction was halted in late 1997.
In 2005 construction resumed with a new completion date estimated at 2012, later updated to 2015. At the restart there were some delays which may again push back the completion date. The builders however, believed that they would be able to make up for lost time during construction.
Cost
Cost overrun has been large. The cost was expected in 1992 to be SEK 1 billion. The cost from 1992 to 1997 was in reality more than SEK 2 billion, for less than half the tunnel length. Since the remaining cost at the beginning of 2005 was calculated to be more than SEK 4 billion, there has been much debate and hesitation as to whether to halt or resume work. The total cost is likely to reach over SEK 10 billion before the project is finished, according to the latest calculation.[1]
Many people involved agree that 10 billion is not worth the benefits, but a number of billions has been spent already and it was considered best to countinue the construction.