Hugh C. Bailey Science Center
Former namesBiology and Chemistry Building
General information
Architectural styleSpanish-mission
Address1500 North Patterson Street
Cost$23 million
OwnerValdosta State University
Technical details
Floor count3
Floor area148,165 square feet[1][2]
Design and construction
Architecture firmIngram, Parris Group

The Hugh C. Bailey Science Center at Valdosta State University in Valdosta, Georgia serves as the home of the Biology and Chemistry Departments. The facility is named after former VSU President Hugh C. Bailey who served from 1978 to 2001.[3]

History

Bailey Science Center came about as a means of dealing with overcrowding and the lack of space for future growth facing both the Biology and Chemistry Departments.[4]

The new science building was designed to take pressure off of Nevins Hall which had served as the science building at Valdosta State for nearly 30 years. Nevins remaining occupants after the new facility was completed and the Biology and Chemistry departments had moved included the departments of mathematics, computer science, physics, astronomy, and geo-sciences.[5]

Construction

The formal ground breaking ceremony was Sept. 26, 1996, and actual construction began in the summer of 1998 on the approximately 148,000 square foot building. The construction contract was awarded to M.M. Parrish Construction, Inc. of Gainesville, Fla. and the building architecture was designed by Ingram, Parris Group (IPG) of Valdosta. IPG enlisted the assistance of Lord, Aeck and Sargent of Atlanta and Research Facilities Design of San Diego to lend their design expertise in the area of laboratory facilities.[4]

Contracted in 1998, the facility was scheduled to be completed by October 15, 1999 at a cost of $19,296,000. But ultimately the building was not completed until late 2000 with a greater cost of around $22.4 million. Faculty of the Biology and Chemistry departments began moving into the new structure in November of that year and classes were first held in January of 2001. The structure was dedicated in April 23, 2001 and renamed in honor of High C. Bailey, former VSU president.[5]

Features

The Bailey Science Center has 22 teaching and 19 research laboratories that occupy the entire north side of the building. In addition, it has four greenhouses on the rooftop; 11 classrooms, including four 48 seat classrooms, and one 96 seat classroom[6]; a large auditorium which seats 275, and a smaller auditorium which seats 148; two conference rooms and 41 offices.[4]

References

  1. ^ John Portman & Associates. "Valdosta State University Campus Master Plan Update". December 2003. Page 2.
  2. ^ http://www.ipgarchitects.com/vsubiology.htm
  3. ^ http://www.valdosta.edu/news/releases/bailey.120800/
  4. ^ a b c Boyd, Thressea H. VSU Alumni Voice, Summer 2001, Vol.1, No.3, Office of University Relations for the Office of Alumni Relations, Colson Printing Valdosta, Ga.
  5. ^ a b English, Victoria. “Faculty Begins Move”. Valdosta Daily Times. November 21, 2000
  6. ^ http://www.valdosta.edu/biology/facilities.shtml