Jump to content

Lincs Wind Farm

Coordinates: 53°11′00″N 0°29′00″E / 53.1833°N 0.4833°E / 53.1833; 0.4833
From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Xiiophen (talk | contribs) at 20:18, 17 February 2016. The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Lincs Wind Farm
Lincs Offshore Wind Farm turbines behind those of Lynn and Inner Dowsing
Map
CountryEngland, United Kingdom
LocationNorth Sea
Coordinates53°11′00″N 0°29′00″E / 53.1833°N 0.4833°E / 53.1833; 0.4833
StatusOperational
Construction began2010
Commission dateSeptember 2013
Construction cost£1 billion
OwnersCentrica
DONG Energy
Siemens
Operator
Wind farm
TypeOffshore
Distance from shore8 km (5.0 mi)
Hub height100 m (328 ft)
Rotor diameter120 m (394 ft)
Site area
  • 35 km2 (14 sq mi)
Power generation
Units operational75 × 3.6 MW
Make and modelSiemens Wind Power SWT-3.6
Units planned75
Nameplate capacity270 MW
External links
CommonsRelated media on Commons

The Lincs Wind Farm is a 270 MW offshore wind farm 8 kilometres (5.0 mi) off Skegness on the east coast of England. The total cost of the project is estimated at £1 billion including electrical transmission links. The farm was completed in 2013. It is adjacent to the smaller Lynn and Inner Dowsing Wind Farm.

History

Centrica acquired the Lincs Wind Farm project in 2004 from Renewable Energy Systems, in 2008 the company obtained planning permission for the project.[1][2]

In December 2009 DONG Energy and Siemens Project Ventures jointly acquired 50% of the project (25% share each) for £50 million, plus 50% of the capital cost of the project.[3]

Preparatory construction work for the development included the extension of the national-grid electricity substation at Walpole, Norfolk, which began in April 2009.[4][note 1] In June 2010 Siemens obtained the contract for the offshore electrical substation (£101 million).[7] Transmission cables from offshore to onshore electrical substations were installed in 2010–2011.[4][8] Construction of the offshore facilities of the wind farm began in 2011, with the installation of the offshore electricity substation foundations.[9] The Port of Hull was selected as one of the logistics bases for the wind farm turbine installation, supplying wind tower transition pieces. Jack-up barge JB114 arriving at the port in March 2012.[10] Great Yarmouth was also used as a base for the wind farm installation.[11]

Construction of the offshore 33 kV to 132 kV substation (structure sub-contracted to McNulty Offshore Construction/Atkins PLC.[12]) and of the onshore 132 kV to 400 kV substation was completed by April 2012.[13]

In August 2011, the consortia of DONG, Siemens, and Centrica began to seek financing for the £1 billion project, committing to providing £166.7, £75 and £333.3 million respectively (£575 million total). In June 2012 the consortia obtained financing for the project with £425 million of nonrecourse debt facilities provided from a consortium of 10 banks. Approximately 75%, of the project cost was for the wind farm installation, the remainder for the high voltage electricity transmission link.[14]

Construction began in 2010; installation of the 75-monopile tower foundation by MT Højgaard was completed by June 2012, with the underwater installation phase completed by September 2012.[15] The first generator had been installed by 14 July 2012.[16] The wind farm was scheduled become operational in the second half of 2012, and be complete by 2013:[17] the final turbine was installed by March 2013;[18] and the wind farm officially opened by Deputy Prime Minister Nick Clegg in August 2013,[19][20] with commissioning complete in September 2013.[21] The license for the electrical transmission link was awarded to TC Lincs OFTO Limited for £308 million in late 2014.[22]

Technical description

The scheme has 250 MW of generating capacity, with an additional 20 MW of turbine generating capacity constructed within the nearby Lynn Wind Farm and Dowsing Wind Farm but connected to the Lincs project transmission system.[23] The project uses 75 three blade 3.6 MW Siemens wind turbines. The wind turbines have 120 metres (390 ft) rotor diameter machines with 58.5 metres (192 ft) blades with a hub height of 100 metres (330 ft) on cylindrical steel towers. The turbines were installed in 10 to 15 metres (33 to 49 ft) water depth, with a spacing of approximately 500 metres (1,600 ft) within a 35 square kilometres (14 sq mi) wind farm.[8]

Transmission of electrical power to land is by 145 kV cables supplied by Nexans. Transmission voltage is 132 kV to land, being increased to 400 kV at Walpole substation for grid connection.[8]

The operation and maintenance base for the wind farm is be based at Grimsby.[24]

The wind farm has an expected lifespan of 40 years, with electrical equipment and wind turbines expected to be replaced after 20 years. After the end of the project's lifespan the farm is to be decommissioned, including removal of turbines and electrical equipment, and removal of offshore foundations or cut off to seabed level or lower. Connecting cables are not scheduled to be removed.[25]

See also

Notes

  1. ^ Lincs, Docking Shoal and Race Bank wind farms were to share the same onshore cable export route, and onshore substation.[5] The environmental statement for the onshore works was submitted as part of the Lincs Wind Farm application.[6]

References

  1. ^ "Centrica gains government consent for second generation offshore wind farm" (PDF) (Press release). Centrica. 21 October 2008. Archived from the original (PDF) on 13 February 2015.
  2. ^ "Centrica's Lincolnshire development leads offshire windfarm stampeded". Utility Week. 29 October 2008.
  3. ^ Sources:
  4. ^ a b "Lincs Offshore Wind Farm Construction Update" (PDF). Centrica. March 2012. Archived from the original (PDF) on 30 April 2015. The power from Lincs will be transmitted to the National Grid substation at Walpole ... Work to build an extension to the substation commenced in 2010 to enable the power to be transformed from 132 kV to 400 kV ... Civil works commenced at the National Grid substation site at Walpole in April last year
  5. ^ "Race Bank Offshore Wind Farm - Environmental Statement Non-Technical Summary" (PDF). Centrica. January 2009. p. 3. Archived from the original (PDF) on 30 April 2015.
  6. ^ Lincs Offshore Wind Farm ES : Non-Technical Summary (January 2007) pp. 3, 5, 11
  7. ^ "Siemens wins new £101 million order to connect Lincs offshore wind farm to the UK grid" (Press release). Siemens. 28 June 2010.
  8. ^ a b c "Centrica Lincs Offshore Wind Project, United Kingdom". Power Technology. Retrieved 4 April 2012. {{cite news}}: Cite has empty unknown parameter: |1= (help)
  9. ^ Sources:
  10. ^ Sources:
  11. ^ "Lincs Offshore Wind Farm". www.4coffshore.com. 4C Offshore. Retrieved 24 January 2013.
  12. ^ "Siemens LINCS OSS - McNulty Offshore Construction". www.mcnultyoffshore.com. Retrieved 8 June 2012.
  13. ^ "Lincs Offshore Wind Farm Construction Update" (PDF). Centrica. April 2012. Archived from the original (PDF) on 30 April 2015. Construction of the 3,000 tonne offshore substation, .. which will transform power from the wind farm from 33 kV to 132 kV .. is now complete, ... It has been built by McNulty, a subcontractor to Siemens Transmission and Distribution Limited, based in South Shields. [..] The testing and energisation of the onshore substation at Walpole, .. is now complete. This substation will boost the power from 132 kV to 400 kV {{cite web}}: Cite has empty unknown parameter: |1= (help)
  14. ^ Sources:
  15. ^ Sources:
  16. ^ "Lincs Wind Farm August 2012" (PDF). Centrica. August 2012.[dead link]
  17. ^ "£425 million Lincs Wind Farm project financing agreements finalised" (Press release). Centrica. 7 June 2012.
  18. ^ "UK: Final turbine installed at Lincs Offshore Wind Farm". worldmaritimenews.com. 3 April 2013.
  19. ^ Lincs offshore wind farm officially opened by Deputy Prime Minister Nick Clegg (PDF) (press release), Siemens, 1 August 2013
  20. ^ "Nick Clegg opens Skegness offshore wind farm". BBC News. 2 August 2013.
  21. ^ "Lincs offshore wind farm: mission complete". Centrica. 27 September 2013.
  22. ^ "TCP pockets £308m Lincs licence". renews.biz. 4 November 2014.
  23. ^ "Lincs Project History" (PDF). Centrica. Archived from the original (PDF) on 30 December 2014.
  24. ^ Sources:
  25. ^ "LINCS Offshore Wind Farm Decommissioning Plan: On behalf of Lincs Wind Farm Limited" (PDF). Centrica. December 2010. pp. 1–2. Archived from the original (PDF) on 13 February 2015.

Sources

Centrica
Other