===Early planning and delays=== |
===Early planning and delays=== |
||
A part of the right-of-way of the present MRT-7 project can be traced to the original [[MRT Line 4 (Metro Manila)|Line 4]] proposal in 1995, when [[Ayala Land]] and a consortium of French (including Javlon International, [[Bouygues]], and [[SOFRETU]]) proposed a 15.1 km line from [[Old Bilibid prison|Old Bilibid]] near the [[Recto Avenue]] in Manila to [[Batasan Hills|Batasan]] in Quezon City.<ref>{{Cite web |last=C. Samonte |first=Severino |date=March 23, 2023 |title=MRT Line-7 was planned as LRT Line 4 during FVR's time in 1995 |url=https://www.pna.gov.ph/opinion/pieces/652-mrt-line-7-was-planned-as-lrt-line-4-during-fvrs-time-in-1995 |access-date=May 20, 2024 |website=Philippine News Agency}}</ref><ref>{{Cite web |last=International1997-04-01T10:00:00+01:00 |first=Railway Gazette |title=Manila LRT expansion accelerated |url=https://www.railwaygazette.com/news/manila-lrt-expansion-accelerated/27454.article |access-date=2024-05-20 |website=Railway Gazette International |language=en}}</ref> This was also supposed to have a rolling stock of [[Light rail|light rail vehicles]] (LRVs), and in the 2005 proposal, the line would have utilized [[Electric multiple unit|electric multiple units]] (EMUs) as its rolling stock. |
|||
⚫ | |||
⚫ | As part of the Metro Manila Urban Transportation Integration Study published by the [[Japan International Cooperation Agency]] in 1999, which included the Line 4 plan, it called for the construction of a {{Convert|22.8|km|abbr=on}} [[elevated railway]] between Recto Avenue in Manila and [[Novaliches]] in Quezon City. A branch line, which would either be an [[automated guideway transit]] or [[Bus rapid transit|busway]], would have shuttle commuters to and from [[San Mateo, Rizal]]. This proposal would be later split into MRT-7 and the [[MRT Line 8]] proposal. The section of this route between the Quezon Memorial Circle and Novaliches became Line 7 while the rest of the proposed line became Line 8.<ref>{{Cite report|first=Shizuo|last=Iwata|title=Final Report Summary|work=Metro Manila Urban Transportation Integration Study |url=https://openjicareport.jica.go.jp/pdf/11580446.pdf|publisher=[[Japan International Cooperation Agency]]|date=March 5, 1999|access-date=October 2, 2021|archive-date=October 2, 2021|archive-url=https://web.archive.org/web/20211002110225/https://openjicareport.jica.go.jp/pdf/11580446.pdf|url-status=live}}</ref> |
||
On August 27, 2001, an early proposal of the MRT-7 project was submitted to the [[Department of Transportation (Philippines)|Department of Transportation and Communications]] (now the Department of Transportation).<ref name="July2021update">{{Cite news|first=Lea|last=Devio|title=MRT-7 60.93% complete|work=The Manila Times|url=https://www.manilatimes.net/2021/07/23/news/national/mrt-7-6093-complete/1808057|date=July 23, 2021|access-date=July 23, 2021|url-status=live|archive-url=https://web.archive.org/web/20210723030806/https://www.manilatimes.net/2021/07/23/news/national/mrt-7-6093-complete/1808057|archive-date=July 23, 2021}}</ref> The Investment Coordination Committee (ICC) of the [[National Economic and Development Authority]] (NEDA) first approved a version of the MRT Line 7 project in March 2004; this initial approval was provisional and contingent on the project's impact on the government's deficit reduction program. It had been submitted as an [[unsolicited proposal]] under the [[build–operate–transfer]] scheme by the Universal LRT Corporation, a [[consortium]] consisting of [[Alstom]], EEI Corporation, [[TE Connectivity|Tyco Electronics]], and others.<ref name=ferriols2004/> NEDA subsequently authorized the $1.2 billion project's construction the following August, citing the proponents' willingness to comply with the ICC's requirements, with construction slated to begin in 2005 and a targeted opening date in 2007.<ref name=reyes2004/><ref name=cabacungan2004/> In October 2004, Universal LRT Corporation signed an agreement with the Manila Banking Corporation to purchase {{convert|193|ha|acre|abbr=off}} of property in Bulacan for ₱1 billion, stating it would develop this property to complement the rail line.<ref name=batino2004/> |
On August 27, 2001, an early proposal of the MRT-7 project was submitted to the [[Department of Transportation (Philippines)|Department of Transportation and Communications]] (now the Department of Transportation).<ref name="July2021update">{{Cite news|first=Lea|last=Devio|title=MRT-7 60.93% complete|work=The Manila Times|url=https://www.manilatimes.net/2021/07/23/news/national/mrt-7-6093-complete/1808057|date=July 23, 2021|access-date=July 23, 2021|url-status=live|archive-url=https://web.archive.org/web/20210723030806/https://www.manilatimes.net/2021/07/23/news/national/mrt-7-6093-complete/1808057|archive-date=July 23, 2021}}</ref> The Investment Coordination Committee (ICC) of the [[National Economic and Development Authority]] (NEDA) first approved a version of the MRT Line 7 project in March 2004; this initial approval was provisional and contingent on the project's impact on the government's deficit reduction program. It had been submitted as an [[unsolicited proposal]] under the [[build–operate–transfer]] scheme by the Universal LRT Corporation, a [[consortium]] consisting of [[Alstom]], EEI Corporation, [[TE Connectivity|Tyco Electronics]], and others.<ref name=ferriols2004/> NEDA subsequently authorized the $1.2 billion project's construction the following August, citing the proponents' willingness to comply with the ICC's requirements, with construction slated to begin in 2005 and a targeted opening date in 2007.<ref name=reyes2004/><ref name=cabacungan2004/> In October 2004, Universal LRT Corporation signed an agreement with the Manila Banking Corporation to purchase {{convert|193|ha|acre|abbr=off}} of property in Bulacan for ₱1 billion, stating it would develop this property to complement the rail line.<ref name=batino2004/> |
||
Line 309: | Line 311: | ||
In 2021, the project was realigned. Due to right-of-way issues, the original site of the [[Tala station|Tala]] and [[San Jose del Monte station]] was relocated, and the guideway leading to the station itself was realigned, now passing through the [[Quirino Highway]] alignment instead of passing through Pangarap Village, which has been disputed for years.<ref>{{Cite news|first=Demie|last=Dangla|title=Pangarap Village residents decry harassment over land dispute|url=https://manilatoday.net/pangarap-village-residents-decry-harassment-over-land-dispute/|work=Manila Today|date=June 18, 2015|access-date=July 22, 2021|archive-url=https://web.archive.org/web/20180204085519/https://manilatoday.net/pangarap-village-residents-decry-harassment-over-land-dispute/|archive-date=February 4, 2018}}</ref> |
In 2021, the project was realigned. Due to right-of-way issues, the original site of the [[Tala station|Tala]] and [[San Jose del Monte station]] was relocated, and the guideway leading to the station itself was realigned, now passing through the [[Quirino Highway]] alignment instead of passing through Pangarap Village, which has been disputed for years.<ref>{{Cite news|first=Demie|last=Dangla|title=Pangarap Village residents decry harassment over land dispute|url=https://manilatoday.net/pangarap-village-residents-decry-harassment-over-land-dispute/|work=Manila Today|date=June 18, 2015|access-date=July 22, 2021|archive-url=https://web.archive.org/web/20180204085519/https://manilatoday.net/pangarap-village-residents-decry-harassment-over-land-dispute/|archive-date=February 4, 2018}}</ref> |
||
{{as of|2023|1|31|df=US}}, the project is 66.07% complete.<ref>{{cite web|url=https://www.congress.gov.ph/photojournal/zoom.php?photoid=4499|title=House Tackles Dotr's Railway Projects Status, Urges Agency To Fix Project Delays|author=<!--Not stated-->|date=16 February 2023|publisher=Press and Public Affairs Bureau|website=[[House of Representatives of the Philippines]]|access-date=21 February 2023|archive-date=February 20, 2023|archive-url=https://web.archive.org/web/20230220213359/https://www.congress.gov.ph/photojournal/zoom.php?photoid=4499|url-status=live}}</ref> The line was planned to undergo "demonstration runs" by 2023 and full operations by 2024–2025; but was later deemed no longer feasible, targeting full operations by the second quarter of 2025 instead,<ref name="latestupdate" /> with DoTr Project Management Service (PMS) Director Eduardo D. Mangalili citing the completion of the depot as the main factor.<ref name="latestupdate" /> |
{{as of|2023|1|31|df=US}}, the project is 66.07% complete.<ref>{{cite web|url=https://www.congress.gov.ph/photojournal/zoom.php?photoid=4499|title=House Tackles Dotr's Railway Projects Status, Urges Agency To Fix Project Delays|author=<!--Not stated-->|date=16 February 2023|publisher=Press and Public Affairs Bureau|website=[[House of Representatives of the Philippines]]|access-date=21 February 2023|archive-date=February 20, 2023|archive-url=https://web.archive.org/web/20230220213359/https://www.congress.gov.ph/photojournal/zoom.php?photoid=4499|url-status=live}}</ref> The line was planned to undergo "demonstration runs" by 2023 and full operations by 2024–2025; but was later deemed no longer feasible, targeting full operations by the second quarter of 2025 instead,<ref name="latestupdate" /> with DoTr Project Management Service (PMS) Director Eduardo D. Mangalili citing the completion of the depot as the main factor.<ref name="latestupdate" /> However, the right-of-way issues, especially in San Jose Del Monte, continue to delay the project, and the DOTr expects partial operations from North Avenue to Lagro on the same date. The local government of SJDM informed DOTr that it would divert the station to another location.<ref>{{Cite web |last=CEDTyClea |date=2024-05-19 |title=Completion of SMC’s MRT-7 delayed on RoW issues in Bulacan segment — DoTr |url=https://www.bworldonline.com/corporate/2024/05/20/596082/completion-of-smcs-mrt-7-delayed-on-row-issues-in-bulacan-segment-dotr/ |access-date=2024-05-20 |website=BusinessWorld Online |language=en-US}}</ref> |
||
==Station design and layout== |
==Station design and layout== |
Revision as of 11:32, 20 May 2024
MRT Line 7 | |
---|---|
Overview | |
Status | Under construction |
Owner | Department of Transportation |
Line number | 7 |
Locale | Metro Manila and Bulacan |
Termini | |
Stations | 14[1] |
Service | |
Type | Rapid transit |
System | Manila Metro Rail Transit System |
Services | 1 |
Operator(s) | SMC Mass Rail Transit 7 Incorporated[1] |
Rolling stock | Class 000 EMUs |
Daily ridership | 300,000 (initial) 850,000 (design capacity) |
History | |
Planned opening | 2027 (full)[2] |
Technical | |
Line length | 24.069 km (14.956 mi) |
Number of tracks | Double-track |
Character | Grade separated |
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge |
Electrification | 750 V DC third rail[3] |
Average inter-station distance | 1.85 km (1.15 mi) |
The Metro Rail Transit Line 7, also known as MRT Line 7 or MRT-7, is a rapid transit line under construction in the Philippines. When completed, the line will be 22.8 kilometers (14.2 miles) long, with 14 stations, and the first line to have a third rail electrification.[3] The line runs in a northeast–southwest direction, beginning at San Jose del Monte, Bulacan up to the North Triangle Common Station in North Avenue, Quezon City.
First planned in 2001 and approved in 2004,[4][5] the 25-year concession agreement was signed in 2008 between the Philippine government and the project's original proponent, Universal LRT Corporation.[6] However, construction has been repeatedly delayed due to right-of-way issues. The project was re-approved in 2013,[6] while funding for the project was obtained in 2016.[7] Construction on the line began the following year and is slated to open by 2025.[8][2] The project will cost an estimated ₱62.7 billion (US$1.54 billion),[9] with additional plans are laid for capacity expansion in order to accommodate the possible increase in passenger ridership in the future.
It is integrated with the public transit system in Metro Manila, and passengers also take various forms of road-based public transport, such as buses, to and from a station to reach their intended destination.
Route
The line will start at San Jose del Monte located in Bulacan and will end at the North Triangle Common Station in Quezon City. The line is mostly elevated and erected either over or along the roads covered, with underground sections between Quezon Memorial and University Avenue, and at San Jose del Monte. The rail line serves the cities that Quirino Highway, Regalado Highway, Commonwealth Avenue, and North Avenue passes through: San Jose del Monte in Bulacan, Caloocan and Quezon City in Metro Manila.
Stations
Upon completion, the line will have 14 stations along its route. Only one station, North EDSA, will initially serve as an interchange with the other metro lines, although two more will be interchanges when Line 8 opens.
No.[10] | Station | Distance (km)[11] | Structure type | Connections | Location | |
---|---|---|---|---|---|---|
Between stations |
Total | |||||
S01 | North EDSA[10] | 1.665 | 0.000 | Elevated | Interchange with Manila LRT Interchange with Manila MRT
|
Quezon City |
S02 | Quezon Memorial Circle[10] | 0.837 | 1.665 | Depressed | Proposed interchange with Manila MRT
| |
S03 | University Avenue | 1.664 | 2.502 | Depressed | Proposed interchange with Manila MRT
| |
S04 | Tandang Sora | 2.254 | 4.166 | Elevated |
| |
S05 | Don Antonio | 0.976 | 6.420 | Elevated |
| |
S06 | Batasan | 1.390 | 7.396 | Elevated |
| |
S07 | Manggahan | 1.472 | 8.786 | At-grade |
| |
S08 | Doña Carmen | 1.145 | 10.258 | Elevated |
| |
S09 | Regalado Avenue[10] | 3.416 | 11.403 | Elevated |
| |
S10 | Mindanao Avenue | 0.800 | 14.819 | Elevated |
| |
S11 | Quirino Avenue | 2.642 | 15.619 | Elevated |
| |
S12 | Sacred Heart | 2.625 | 18.621 | Elevated |
|
Caloocan |
S13 | Tala | 3.183 | 20.886 | Elevated |
| |
S14 | San Jose del Monte | — | 24.069 | Elevated | San Jose del Monte, Bulacan | |
Stations, lines, and/or other transport connections in italics are either under construction, proposed, unopened, or have been closed. |
History
Early planning and delays
A part of the right-of-way of the present MRT-7 project can be traced to the original Line 4 proposal in 1995, when Ayala Land and a consortium of French (including Javlon International, Bouygues, and SOFRETU) proposed a 15.1 km line from Old Bilibid near the Recto Avenue in Manila to Batasan in Quezon City.[13][14] This was also supposed to have a rolling stock of light rail vehicles (LRVs), and in the 2005 proposal, the line would have utilized electric multiple units (EMUs) as its rolling stock.
As part of the Metro Manila Urban Transportation Integration Study published by the Japan International Cooperation Agency in 1999, which included the Line 4 plan, it called for the construction of a 22.8 km (14.2 mi) elevated railway between Recto Avenue in Manila and Novaliches in Quezon City. A branch line, which would either be an automated guideway transit or busway, would have shuttle commuters to and from San Mateo, Rizal. This proposal would be later split into MRT-7 and the MRT Line 8 proposal. The section of this route between the Quezon Memorial Circle and Novaliches became Line 7 while the rest of the proposed line became Line 8.[15]
On August 27, 2001, an early proposal of the MRT-7 project was submitted to the Department of Transportation and Communications (now the Department of Transportation).[4] The Investment Coordination Committee (ICC) of the National Economic and Development Authority (NEDA) first approved a version of the MRT Line 7 project in March 2004; this initial approval was provisional and contingent on the project's impact on the government's deficit reduction program. It had been submitted as an unsolicited proposal under the build–operate–transfer scheme by the Universal LRT Corporation, a consortium consisting of Alstom, EEI Corporation, Tyco Electronics, and others.[5] NEDA subsequently authorized the $1.2 billion project's construction the following August, citing the proponents' willingness to comply with the ICC's requirements, with construction slated to begin in 2005 and a targeted opening date in 2007.[16][17] In October 2004, Universal LRT Corporation signed an agreement with the Manila Banking Corporation to purchase 193 hectares (480 acres) of property in Bulacan for ₱1 billion, stating it would develop this property to complement the rail line.[18]
Universal LRT Corporation, later renamed to now SMC-Mass Rail Transit 7 Incorporated, a subsidiary of San Miguel Corporation (SMC) was selected by the Department of Transportation and Communications to build the line in 2008. The concession agreement of the project was signed on June 18, 2008.[6][19] Construction of the line should have commenced in January 2010, but was postponed several times.[20]
In May 2012, the joint venture of Marubeni Corporation and DMCI was awarded a construction contract.[21] However, after years of delays, SMC planned to conduct a second round of bidding in 2015, due to revised construction cost assumptions.[22]
The current project was approved on November 21, 2013, by the NEDA board, chaired by President Benigno Aquino III, and the project was developed through a public-private partnership (PPP). It has an indicative cost of ₱62.7 billion.[23]
The Department of Finance issued the terms of financial guarantee for the line in 2014, and financial closure for the project was achieved in February 2016.[7] On January 22, 2016, Hyundai Rotem won the US$440.2 million contract with SMC-Mass Rail Transit 7 Incorporated to supply 108 train cars, signalling, communication and power supply systems.[24][25]
Construction
Soil testing and surveying, including pre-construction related activities, were conducted in February 2016. SMC tapped the consortium of Hyundai Rotem and EEI Corporation as the engineering, procurement and construction contractor in the same year.[26] A groundbreaking event was held on April 20, 2016, 15 years after initial development began, and was attended by President Benigno Aquino III.[27] The line was expected to be finished by 2019,[28] but was repeatedly pushed back because of right-of-way issues regarding the acquisition of a 33-hectare (82-acre) land for the San Jose del Monte station, depot, and the intermodal transport terminal (ITT).[29]
More than a year after the groundbreaking ceremony was held, construction on the 22.8-kilometer (14.2-mile) line officially started on August 15, 2017, and has resulted in lane closures and heavy traffic along Commonwealth Avenue and Quirino Highway, both in Quezon City.[8][30][28] The project also includes construction of a 22-kilometer (13.7-mile) highway from the NLEX Bocaue Interchange, up to the proposed intermodal transport terminal (ITT) located near San Jose del Monte station.[1]
Groundbreaking for Batasan station was held on October 7, 2017,[31] while the excavation for the underground guideway at Quezon Memorial Circle is ongoing as of November 2017.[28] Construction of the station and rail track along North Avenue began on January 22, 2018.[32]
Nearly two years since the start of the construction of Line 7, works at the depot commenced on November 26, 2019, according to a statement by the DOTr.[33][34] After two years of court hearings and appeals to obtain a site, the original location of the depot in San Jose del Monte, Bulacan was moved to Quirino Highway in Barangay Greater Lagro, Quezon City. The relocation was found optimal for right-of-way, operational reliability, and maintenance.[33] The depot site was approved by Tugade on June 29, 2019, and the DOTr offered to buy the property from lot owners Century Properties Group, Inc. at the current market value, which was appraised by a Bangko Sentral ng Pilipinas-accredited independent property appraiser.[35] Construction works at the depot started on May 31, 2022, after the land area was cleared.[36]
Originally, the site in Bulacan was subject to a legal case after the property owner questioned the expropriation at the Malolos Regional Trial Court Branch 11. If it was pushed through, the cost of the project would have multiplied ninefold from ₱67.105 million to ₱598.905 million. Transport Assistant Secretary Goddes Hope Oliveros-Libiran stated that it would take forever to resolve the case and it will no longer be pursued. The case in Bulacan has prompted San Miguel to conduct a scheduled partial operation of the line from North Avenue to a station in Fairview in 2021.[37]
In 2021, the project was realigned. Due to right-of-way issues, the original site of the Tala and San Jose del Monte station was relocated, and the guideway leading to the station itself was realigned, now passing through the Quirino Highway alignment instead of passing through Pangarap Village, which has been disputed for years.[38]
As of January 31, 2023[update], the project is 66.07% complete.[39] The line was planned to undergo "demonstration runs" by 2023 and full operations by 2024–2025; but was later deemed no longer feasible, targeting full operations by the second quarter of 2025 instead,[2] with DoTr Project Management Service (PMS) Director Eduardo D. Mangalili citing the completion of the depot as the main factor.[2] However, the right-of-way issues, especially in San Jose Del Monte, continue to delay the project, and the DOTr expects partial operations from North Avenue to Lagro on the same date. The local government of SJDM informed DOTr that it would divert the station to another location.[40]
Station design and layout
The stations will have a standard layout, with a concourse level and a platform level. The concourse is usually above or below the platform, with stairs, escalators and elevators leading down to the platform level. Station concourses will contain ticket booths, which is separated from the platform level by fare gates. Most stations will be designed to be barrier-free inside and outside the station, and trains will have spaces for passengers using wheelchairs.
Stations will either have island platforms and side platforms.
Rolling stock
The line will be operated with 108 rail cars in a three-car configuration. Hyundai Rotem was awarded a $440.2 million contract to supply 108 metro cars, which will be configured into 36 train sets (3 cars per train set, with plans of expanding up to 6 cars per train set). The contractual scope also includes signalling, communications, and power supplies for the metro line. All ordered trainsets have undergone the necessary testing and trials. After being stored in South Korea since 2018 due to a lack of a depot,[29] the 108 railcars are already in the process of being shipped to the Philippines.[41] The first batch of two three-car trainsets arrived in the country on September 6, 2021.[42] The trains were then brought from the Port of Manila to Commonwealth Avenue and were laid on the tracks near the Tandang Sora station from September 11 and 12.[43] On the other hand, the trains are seen to begin test runs by April 2022.[needs update][44] As of December 2021, six trainsets were delivered and laid on the tracks near Tandang Sora station, with the latest deliveries of two trains that were laid in November 2021.[45][46] The trains were unveiled on December 16, 2021.[47] On November 22, 2023, a series of test trials were made for the train sets parked along Commonwealth Avenue, located between Tandang Sora Station and Don Antonio Station. The test were also oversaw by Ramon Ang on December 1, 2023, alongside officials from Hyundai Rotem, Korail, and Rhodium 688.[48] [49]
Rolling stock | First-generation |
---|---|
Image | |
Year | 2018–2019 |
Manufacturer | Hyundai Rotem |
Model | Class 000 |
Number built | 108 cars (36 sets)[24][25] |
Car Length | DM: 21.95 m (72 ft 0 in) T: 21.56 m (70 ft 9 in) |
Train Length | 65.46 m (214 ft 9 in) |
Width | 3.15 m (10 ft 4 in) |
Height | 3.75 m (12 ft 4 in) |
Body material | Stainless steel |
Weight | 115 t (254,000 lb) [clarification needed] |
Configuration | DM1-T-DM2 |
Capacity | 1,168 passengers |
Doors | Pocket sliding; 4 doors per side |
Drive unit | Gear coupling (WN) Drive |
Traction power | 750 V DC third rail |
Traction control | IGBT–VVVF |
Traction motor | 200 kW (270 hp) 3-phase AC induction motor |
Top speed | 90 km/h (55 mph) |
Braking system | Electro-pneumatic |
Safety system(s) | ATP |
Acceleration | 1 m/s2 (3.3 ft/s2) |
Deceleration | 1 m/s2 (3.3 ft/s2) (Service) 1.3 m/s2 (4.3 ft/s2) (Emergency) |
Gauge | 1,435 mm (4 ft 8+1⁄2 in) |
Coupling | Shibata close-contact |
Status | 17 trainsets (51 cars) delivered as of April 2024 |
Depot
The line will maintain an at-grade depot in Barangay Greater Lagro, Quezon City, close to the proximity of La Mesa Watershed.[33] The depot occupies 20 hectares (49 acres) of space and will be the center of the operations and maintenance of the line.[34] It will be capable of handling 150 trains for future expansion of the line.[50]
Expansion
SMC plans for MRT-7 to evolve into a 200-kilometer (120-mile) network. Its main feature is a circumferential mainline comprising the present line, the Airport Access segment to New Manila International Airport, the West Rail Link, and the Phase 2A between the Manila North Harbor and the North Avenue Common Station. Additional branches will also be built in northeastern Metro Manila and Rizal.
Phase 2A
The first proposed extension by phase number is Phase 2A, an unnamed westward extension of the line to Tutuban station via West Avenue, Quezon Avenue and Earnshaw Street before running parallel to the LRT Line 2 after Legarda station.[51] This is similar to an earlier proposal under review, MRT Line 8, under the Philippine National Railways, that has proposed technical specifications identical to the MRT-7. Depending on the deliberations and pending approvals, the two lines may coexist or may be merged.
Phase 2A stations
Name | Line transfers | Barangay | City/Municipality | Nearest Landmarks |
---|---|---|---|---|
Del Monte | none | Phil-Am | Quezon City | None |
Delta | West Triangle | Capitol Medical Center, St. Mary's College | ||
A. Roces | Paligsahan | Fisher Mall, Amoranto Sports Complex | ||
Santo Domingo | Santo Domingo | Santo Domingo Church, UST Angelicum College | ||
D. Tuazon | Santa Mesa Heights | Welcome Rotonda, National Labor Relations Commission | ||
España Boulevard | NSCR España | Sampaloc | Manila | Trabajo Market |
G. Araneta | none | University of Santo Tomas | ||
Legarda | Legarda | San Sebastian Church, University Belt (Mendiola Street section) | ||
Recto | Recto | Santa Cruz | Isetann Recto, Manila City Jail | |
Tutuban | Tutuban Tutuban |
Tondo | Tutuban Center (Old Tutuban Station), Divisoria | |
North Port | Pier 4 North Port Passenger Terminal |
Port of Manila |
Phase 2B (West Rail Link)
Phase 2B is dubbed the West Rail Link project. It will be an airport rail link to New Manila International Airport and traversing the northwest coast of Metro Manila, in similar fashion to the Clark–Buendia Airport Limited Express of the North–South Commuter Railway. It will host express train services and aims to connect the NMIA and Metro Manila within 20 minutes.[52] Thus, it will only have three stations: C2 in Manila, C4 in Navotas, and NMIA. The length of the segment is yet to be determined.[51]
Phase 3 (Airport Access)
With the depot underway, San Miguel Corp. has plans to extend the line further to Bocaue, Bulacan, running parallel to the planned six-lane highway alon the area, which aims to be connected to the North Luzon Expressway.[53] The extension will improve access to Ciudad de Victoria complex, where the Philippine Arena will be within its vicinity.[54] The line will also connect Metro Manila with New Manila International Airport, adding 30.3 kilometers (18.8 miles) to the present line to 53.1 kilometers (33.0 miles).[55] Plans were also laid out connect the airport to the cities of Navotas, Malabon, and Manila, consisting of 19 additional stations, and will travel through the alignment of the LRT 2 Western Extension and the planned MRT 8, before traversing to West Avenue, and finally connecting the planned extension line to the North Triangle Common Station.[56]
This segment shall be operated together with the Philippine National Railways.[55]
Phase 3 stations
Name | Line transfers | Barangay | City/Municipality | Nearest Landmarks |
---|---|---|---|---|
Tungkong Mangga | San Jose del Monte | Tungkong Mangga | San Jose del Monte | Skyline Hospital and Medical Center, Iglesia ni Cristo - Maharlika, College of St. Anthony |
Francisco Homes | none | Mulawin | Grace Medical Center, The Church of Jesus Christ of Latter Day Saints | |
Dulong Bayan | Dulong Bayan | City of San Jose del Monte Government Center, River Park Esplanade | ||
Santa Maria | San Vicente | Santa Maria | Bella Vista | |
Philippine Arena | Tabing Bakod | Philippine Arena, Philippine Sports Stadium | ||
Marilao (Phase 3) | NSCR Marilao | Ibayo | Marilao | SM City Marilao |
NMIA | NMIA | Taliptip | Bulakan | New Manila International Airport |
Phase 4A (Southeast Alignment)
Phase 4A involves the construction of an extension from D. Tuazon station of Phase 2A to Taytay, Rizal. Excluding D. Tuazon, it will have 10 stations running on a northwest–southeast alignment.[51] This project is also similar to the MRT Line 4, except it will run on the same Line 7 network, providing wider access of stations. It will also traverse areas north of Gilmore station towards Quezon Avenue. Line 4 was originally intended to be a monorail system, until it was upgraded to a heavy rail system.
Phase 4A stations
Name | Line transfers | Barangay | City/Municipality | Nearest Landmarks |
---|---|---|---|---|
Araneta Avenue | none | New Manila | Quezon City | De Los Santos Medical Center, St. Luke's Medical Center – Quezon City, Trinity University of Asia |
E. Rodriguez | Kristong Hari | Christ the King Seminary, Barangay Mariana Park, Quezon City Sports Club | ||
Gilmore | Gilmore | New Manila | Gilmore Commercial Plaza, St. Paul University Quezon City | |
Greenhills | none | Greenhills | San Juan | Cardinal Santos Medical Center, Greenhills Shopping Center |
POEA–Ortigas | Wack Wack–Greenhills | Mandaluyong | EDSA Shrine, La Salle Green Hills, Philippine Overseas Employment Administration, Robinsons Galleria, Wack Wack Golf and Country Club | |
Meralco Avenue | (Southeast Alignment Spur) | Ugong | Pasig | Meralco Main Office, The Medical City |
Pasig | None | Rosario | Sto. Rosario de Pasig Church | |
Bonifacio Avenue | (Katipunan branch) | Santo Domingo | Cainta, Rizal | Robinsons Cainta |
L. Wood | None | San Isidro | Taytay, Rizal | Taytay Rotonda Monument |
Taytay | Dolores | Taytay Public Market, Taytay Municipal Hall |
Phase 4B
Phase 4B involves the construction of a spur line between Ortigas Center and V. Mapa station of LRT Line 2. Excluding Meralco Avenue station and V. Mapa, it will have 6 stations traversing a U-shaped right of way.[51]
Phase 5 (Katipunan spur)
Plans were also laid out for a 13.9 kilometers (8.6 miles) additional spur line, known as the MRT 7 Katipunan Spur Line, that aims to connect the line from Tandang Sora station to the LRT Line 2 at Katipunan and Marikina stations; the U.P. Town Center, the Ateneo de Manila University, the Riverbanks Center, and the MRT 4 Cainta Station. The project also consists of 8 additional stations, and will connect areas within Quezon City, Marikina, the eastern parts of Pasig, and Cainta, Rizal. The proposed spur line will traverse through the University of the Philippines Diliman complex, Katipunan Avenue, Aurora Boulevard, Andres Bonifacio Avenue, Sumulong Highway, Mayor Gil Fernando Avenue, and Felix Avenue.[57][58]
Phase 5 stations
Name | Line transfers | Location | Nearest landmarks |
---|---|---|---|
Tandang Sora | Tandang Sora | Matandang Balara, Quezon City | New Era University, Commonwealth Avenue |
Balara | none | University of the Philippines Diliman, MWSS, Balara Filters Park | |
U.P. Town Center | Diliman, Quezon City | U.P. Town Center, C.P. Garcia Avenue (UP), Brgy. Pansol | |
Ateneo | Loyola Heights, Quezon City | Miriam College, Ateneo de Manila University | |
Katipunan | Katipunan | Xavierville Avenue, Aurora Boulevard, Project 2 & 3 | |
Riverbanks | none | Marikina | Riverbanks Center, Barangka, Provident Village |
Sumulong | Marikina City Hall, Amang Rodriguez Memorial Medical Center, Sumulong Highway | ||
Emerald-Marikina | Marikina | Marikina–Infanta Highway, Sta. Lucia East, Robinsons Metro East | |
Bonifacio Avenue | 4 Cainta | Cainta, Rizal | Ortigas Avenue Extension, Cainta Public Market, Robinsons Cainta |
Notes
References
- ^ a b c "MRT Line 7". www.ppp.gov.ph. Public-Private Partnership Center. Archived from the original on April 14, 2021. Retrieved May 5, 2021.
- ^ a b c d Balinbin, Arjay L. (January 25, 2023). "Full MRT-7 operations seen by 2nd quarter 2025". BusinessWorld. Philippines: The Philippine STAR. Archived from the original on January 25, 2023. Retrieved January 25, 2023.
- ^ a b Gines, Ben Jr. (December 17, 2021). "MRT-7 gets new train sets". The Manila Times. Archived from the original on March 11, 2022. Retrieved March 11, 2022.
- ^ a b Devio, Lea (July 23, 2021). "MRT-7 60.93% complete". The Manila Times. Archived from the original on July 23, 2021. Retrieved July 23, 2021.
- ^ a b Ferriols, Des (March 29, 2004). "NEDA body approves MRT Line 7". The Philippine Star. Archived from the original on July 6, 2020. Retrieved December 1, 2021.
- ^ a b c "MRT 7 PROJECT" (PDF). Public-Private Partnership Center. August 2019. Archived (PDF) from the original on January 9, 2022. Retrieved January 9, 2022.
- ^ a b Camus, Miguel R. (February 17, 2016). "With funds secured, Line 7 to run by '19". Philippine Daily Inquirer. Archived from the original on February 17, 2016. Retrieved November 12, 2017.
- ^ a b "Brace for heavy traffic on Commonwealth Avenue as MRT-7 construction starts". GMA News Online. August 13, 2017. Archived from the original on August 14, 2017. Retrieved August 14, 2017.
- ^ Marasigan, Lorenz S. (April 28, 2014). "SMC vows to finish MRT 7 project by August 2019". Business Mirror. Archived from the original on October 4, 2015. Retrieved October 2, 2015 – via Public–Private Partnership Center.
- ^ a b c d 한국철도TV. "필리핀 기차, 한국철도 기술을 담다 🚄 | KORAIL PHILIPPINE BRANCH". YouTube. Archived from the original on December 21, 2022. Retrieved December 21, 2022.
- ^ "THE MRT 7 PROJECT" (PDF). Public-Private Partnership Center. August 2019. Archived (PDF) from the original on August 11, 2022. Retrieved March 10, 2022.
- ^ Cabuenas, Jon Viktor (May 31, 2022). "San Miguel starts construction of MRT7 depot in Bulacan". GMA News. Retrieved May 19, 2024.
- ^ C. Samonte, Severino (March 23, 2023). "MRT Line-7 was planned as LRT Line 4 during FVR's time in 1995". Philippine News Agency. Retrieved May 20, 2024.
- ^ International1997-04-01T10:00:00+01:00, Railway Gazette. "Manila LRT expansion accelerated". Railway Gazette International. Retrieved May 20, 2024.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - ^ Iwata, Shizuo (March 5, 1999). Final Report Summary (PDF). Metro Manila Urban Transportation Integration Study (Report). Japan International Cooperation Agency. Archived (PDF) from the original on October 2, 2021. Retrieved October 2, 2021.
- ^ Reyes, Mary Ann Ll. (August 14, 2004). "Gov't gives green light for $1.2-B MRT-7 intermodal transport system". The Philippine Star.
- ^ Cabacungan Jr., Gil C. (September 14, 2004). "Massive Luzon railway projects to cost at least $5B". Philippine Daily Inquirer.
- ^ Batino, Clarissa S. (October 27, 2004). "MRT-7 group buys P1-B land in Bulacan". Philippine Daily Inquirer.
- ^ Dela Paz, Chrisee (April 14, 2016). "San Miguel Corp forms new company for MRT7". Rappler. Archived from the original on July 22, 2021. Retrieved July 22, 2021.
- ^ Camus, Miguel R. (November 29, 2013). "Construction of Line 7 seen to start in 2014". Philippine Daily Inquirer. Archived from the original on December 1, 2013.
- ^ "Marubeni-DMCI group bags $1B contract to build MRT-7". Agence France-Presse. May 15, 2012. Archived from the original on January 24, 2020. Retrieved December 1, 2021 – via ABS-CBN News.
- ^ Camus, Miguel R. (February 5, 2016). "SMC given 2 weeks to close funding deal for MRT-7". Motioncars. Archived from the original on February 6, 2016. Retrieved December 1, 2021.
- ^ Tan, Kimberly Jane (November 21, 2013). "NEDA approves MRT 7, LRT-1 extension projects". GMA News and Public Affairs. Archived from the original on August 30, 2018. Retrieved August 31, 2021.
- ^ a b Barrow, Keith (January 25, 2016). "Hyundai Rotem trains for Manila Line 7". International Railway Journal. Archived from the original on July 1, 2016. Retrieved July 17, 2016.
- ^ a b "Hyundai Rotem wins $440mn turn-key project in Philippines". Pulse News. January 22, 2016. Archived from the original on September 18, 2016. Retrieved July 17, 2016.
- ^ Daxim L. Lucas (February 15, 2016). "SMC seals financing for P63B MRT-7 commuter project". Inquirer. Archived from the original on February 16, 2016. Retrieved March 15, 2016.
- ^ "Construction Begins for Line 7, Connecting QC to Bulacan". PropertyAsiaPH. April 20, 2016. Archived from the original on April 23, 2016. Retrieved June 6, 2016.
- ^ a b c "DoTr: Expect traffic slowdown on Quirino Highway due to Line 7 construction". GMA News Online. November 5, 2017. Archived from the original on November 5, 2017. Retrieved November 5, 2017.
- ^ a b "Right-of-way issue hounds MRT 7". BusinessWorld Online. August 7, 2018. Archived from the original on August 7, 2018. Retrieved December 5, 2018.
- ^ "Motorists told to avoid Quirino Highway due to MRT7 construction". Rappler. November 5, 2017. Archived from the original on November 5, 2017. Retrieved November 8, 2017.
- ^ Cordero, Ted (October 7, 2017). "Concrete pouring at MRT-7 Batasan Station in QC begins". GMA News Online. Archived from the original on October 7, 2017. Retrieved October 28, 2017.
- ^ Galvez, James Konstantin (January 20, 2018). "Heavy traffic expected with MRT-7 construction". The Manila Times. Archived from the original on January 23, 2018. Retrieved January 23, 2018.
- ^ a b c Cordero, Ted (November 27, 2019). "MRT7 depot works commence as QC court grants DOTr, SMMRT7 writ of possession". GMA News Online. Archived from the original on October 6, 2021. Retrieved November 29, 2019.
- ^ a b Galvez, Daphne (November 27, 2019). "MRT-7 depot construction starts as courts grant DOTr, SMC right of way". newsinfo.inquirer.net. Archived from the original on November 28, 2019. Retrieved November 29, 2019.
- ^ Subingsubing, Krixia (November 28, 2019). "MRT 7 on track for partial opening in 2021". business.inquirer.net. Archived from the original on November 28, 2019. Retrieved November 29, 2019.
- ^ Cordero, Ted (May 31, 2022). "San Miguel starts construction of MRT7 depot in Bulacan". GMA News. Archived from the original on May 31, 2022. Retrieved May 31, 2022.
- ^ Balinbin, A.L. (November 28, 2019). "MRT-7 clears key hurdle". BusinessWorld. Archived from the original on April 12, 2020. Retrieved November 29, 2019.
- ^ Dangla, Demie (June 18, 2015). "Pangarap Village residents decry harassment over land dispute". Manila Today. Archived from the original on February 4, 2018. Retrieved July 22, 2021.
- ^ "House Tackles Dotr's Railway Projects Status, Urges Agency To Fix Project Delays". House of Representatives of the Philippines. Press and Public Affairs Bureau. February 16, 2023. Archived from the original on February 20, 2023. Retrieved February 21, 2023.
- ^ CEDTyClea (May 19, 2024). "Completion of SMC's MRT-7 delayed on RoW issues in Bulacan segment — DoTr". BusinessWorld Online. Retrieved May 20, 2024.
- ^ "Trains for MRT-7 project set to arrive next week: SMC". Philippine News Agency. September 1, 2021. Archived from the original on September 1, 2021. Retrieved September 1, 2021.
- ^ Sarao, Zacarian (September 7, 2021). "Two train sets for MRT 7 arrive in Manila". Philippine Daily Inquirer. Archived from the original on September 7, 2021. Retrieved September 8, 2021.
- ^ "SMC starts installation of first MRT7 train sets from Korea". GMA News. September 13, 2021. Archived from the original on September 13, 2021. Retrieved September 13, 2021.
- ^ Cabuenas, Jon Viktor D. (September 20, 2021). "MRT7 trains to be seen running by April 2022". GMA News. Archived from the original on September 21, 2021. Retrieved September 21, 2021.
- ^ "Six newly installed train sets for the Metro Rail Transit Line 7 (MRT-7) project were spotted along Commonwealth Avenue, Quezon City on Wednesday". Facebook. December 1, 2021. Retrieved December 1, 2021.
- ^ "Two new train sets of MRT-7 have arrived as of today morning along Commonwealth Avenue". Facebook. November 13, 2021.
- ^ "New train sets for MRT-7 unveiled". CNN Philippines. December 16, 2021. Archived from the original on December 16, 2021. Retrieved December 16, 2021.
- ^ "RSA checks MRT-7 test run: QC to Bulacan in 35 minutes… soon!". bilyonaryo.com. December 3, 2023.
- ^ "MRT 7 Test Run (Trainset 28), 11/22/2023".
- ^ Ombay, Giselle (December 15, 2021). "DOTr says MRT-7 now 62% complete". GMA News. Archived from the original on December 15, 2021. Retrieved December 15, 2021.
- ^ a b c d NMIA Multimodal Transportation Network. SMC Infrastructure. Archived from the original on August 30, 2021. Retrieved August 30, 2021.
- ^ Gonzales, Iris (August 31, 2018). "SMC plans MRT Loop to link Bulacan airport". Philippine Star. Archived from the original on August 31, 2018. Retrieved August 30, 2021.
- ^ Amojelar, Darwin G. (December 8, 2019). "SMC wants to extend MRT Line 7 to Bocaue". Manila Standard. Archived from the original on December 2, 2021. Retrieved December 10, 2019.
- ^ Camus, Miguel R. (December 9, 2019). "MRT 7 extension to Bocaue eyed". business.inquirer.net. Archived from the original on August 30, 2021. Retrieved December 10, 2019.
- ^ a b "MRT 7 Airport Express". www.ppp.gov.ph. Public-Private Partnership Center. Archived from the original on June 11, 2020. Retrieved November 1, 2020.
- ^ "Bulacan Airport MRT Seven Masterplan". www.puregroupofcompanies.com. Archived from the original on June 29, 2021. Retrieved June 29, 2021.
- ^ http://www.dbm.gov.ph/wp-content/uploads/BESF/BESF2021/I4.pdf&ved=2ahUKEwihkJ7SlLLuAhUqwYsBHV0zChwQFjABegQIAhAF&usg=AOvVaw3qFFXQTmQDfpiyBj9bQ0qy&cshid=1611409381609 [permanent dead link ]
- ^ "MRT 7 Katipunan Spur Line Project". PPP Center. Archived from the original on June 9, 2020.